Title: 3.NEW SCHOOL K-8 NO. 274 (103RD STREET AND CONNIE JEAN ROAD): Revised Project and Revised Project Budget DCSB Project No. C-90470
Requested Action:
THAT THE DUVAL COUNTY SCHOOL BOARD APPROVE A REVISED PROJECT AND PROJECT BUDGET, INCREASING THE PROJECT BUDGET IN THE AMOUNT OF $2,000,000 TO A REVISED TOTAL BUDGET OF $42,100,000, AND A BUDGET AMENDMENT RESOLUTION.
Summary Explanation and Background:
The project is for the construction of a new K-8 school for 1468 student stations.
This budget revision is necessary to accommodate an increase in student stations and classrooms for middle school and ESE students.
This project is listed on the Board approved Five Year Plan 07-09.
New Century Commission Recommendation/OPPAGA Recommendation/Council of Great City Schools Recommendation:
R134
Financial Impact (Including HR/headcount/Source of Funds):
The total budget for this project is $42,100,000.
The planned funding source for this project is COPS and millage.
For Additional Information, contact:
Mr. Andrew N. Eckert, P.E., Executive Director, Design and Construction Services, 390-2498
Mr. James Womack, Director, Design and Construction Services, 390-2310
Mr. Antonio Gimenez, Project Manager, Design and Construction Services, 390-2945
Mr. Doug Ayars, Jr., P.E., Chief Operating Officer, 390-2007
|