6.  Athletic Facilities Improvements at Andrew Jackson High School No. 35: Phase III (construction) DOCUMENTS

DCSB Project No. M-85350

Requested Action:
THAT THE DUVAL COUNTY SCHOOL BOARD APPROVE PHASE III (CONSTRUCTION) DOCUMENTS AS PREPARED BY THE FIRM OF JUNCK & WALKER ARCHITECTS/PLANNERS, Inc., FOR Athletic Facilities Improvements at Andrew Jackson High School No. 35.

Summary Explanation and Background:

This project is to renovate and remodel the field house and concession stands and to provide ADA upgrades to the Andrew Jackson stadium.

 

Phase III (construction) documents will be available for review in the fifth floor conference room of the Central Administration Building after 1:00 p.m. the day of the School Board meeting or at other times by contacting the Facilities Services Department.

 

This project was listed on the Board‑approved 06-07 Major Maintenance List, line item no. 52.

New Century Commission Recommendation/OPPAGA Recommendation/Council of Great City Schools Recommendation:
R134

Financial Impact (Including HR/headcount/Source of Funds):

The design is proceeding on schedule and the construction, when approved, is scheduled to be completed by August 2008.

 

The total budget for this project is $1,240,000.

 

The planned funding source for this project is millage.

For Additional Information, contact:

Mr. Andrew N. Eckert, P.E., Executive Director, Design and Construction Services, 390-2498

 

Mr. James Womack, Director, Design and Construction Services, 390-2310 

 

Mr. Antonio Gimenez, Project Manager, Design and Construction Services, 390-2945 

 

Mr. Doug Ayars, Jr., P.E., Chief Operating Officer, 390-2007