Title: REVISED ITEM: Additions, Remodeling, Renovations and Site Improvements at Woodland Acres Elementary School No. 89: Change Order No. 7 for Beers Skanska, Inc. DCSB Project No. C-90780
Requested Action:
RECOMMEND APPROVAL OF CHANGE ORDER NO. 7 IN THE ADDITIVE AMOUNT OF $421,904.72, TO A REVISED CONTRACT AMOUNT OF $5,417,176.24, WITH A 23 27-DAY TIME EXTENSION TO THE CONTRACT WITH BEERS SKANSKA, INC., AND A BUDGET AMENDMENT RESOLUTION.
Summary Explanation and Background:
This project is to provide a new ten-classroom building to replace existing portables, a new cafetorium building, remodeling of existing cafetorium into one art lab and three resource classrooms; renovations of classrooms in Buildings No. 1 and No. 2 and associated site work. The parking will be expanded with a new parent pick-up and relocation of the bus loop.
This project was listed on the Board approved Long Range Capital Outlay Plan Schedule.
It is the recommendation of the design professional and Facilities Services Division staff that this change be approved.
New Century Commission Recommendation:
R134
Financial Impact:
Change Order No. 7 = $421,904.72 Rev. Const. Contract = $5,417,176.24
With approval of this change order, the total of all changes to this contract to date is $567,175.72.
The amount of this change is within budgeted funds.
The planned funding source for this project is millage.
For Additional Information, contact:
McGlade L. Holloway, 390-2007
Tom Young, 390-2279
George L. Latimer, 390-2096
|