Project
|
|
|
School
|
|
Phase
|
Budget
|
Construction
|
|
|
Number
|
Project Description
|
PM
|
No.
|
Name
|
Current
|
Actual
%
Complete
|
Architect/Engineer
|
Contractor
|
Project
|
Const.
|
Start
|
SC Date
|
Comments
|
|
|
Design & Install Hurricane Protection
|
AA
|
3226
|
Crystal Springs Elementary
|
Bidding
|
|
Baker Klein Engineering
|
AJAX
|
$144,996
|
$
|
7/1/2009
|
|
|
|
C-90470
|
New K-8"DD"(K-8)
|
KE
|
3274
|
|
Construction
|
89%
|
JSA
|
Ajax
|
$42,100,000
|
$35,800,000
|
1/7/2008
|
6/6/2009
|
Construction proceeding - 89% complete
|
|
C-90640
|
Phase Out/Update Portables Districtwide
|
BA
|
3225
|
Seabreeze Elementary
|
Construction
|
|
n/a
|
Allstate
|
$3,000,000
|
$500,000
|
|
8/1/2005
|
|
|
C-90650
|
New High School Campus with Athletic Facities
|
KT
|
3090
|
Englewood High
|
Construction
|
50%
|
Schenkel Shultz Architects
|
WG Mills
|
$103,625,000
|
$76,550,000
|
4/14/2008
|
3/14/2010
|
Building Construction and Roadway Construction proceeding on schedule. Roadway 50% paved to school, Building Structures are complete, Fieldhouse 95% complete, Building #2 is 75% complete with finishes continuing, Building #1 45% complete with framing and infrastructure in process, sitework continues with parking lots being prepared for asphalt, Football stadium bleachers complete, Ball Field construction slated to begin by 5/1.
|
|
C-91070
|
New k-8 school next to High School Triple A
|
TG
|
|
|
Pre-Planning
|
|
JSA/Perkins and Will, pending
|
TBD
|
$42,100,000
|
$35,000,000
|
10/5/2009
|
|
A/E selected, contract negotiation started
|
|
C-91080
|
Conversion of existing North Shore ES to a K-8 school
|
KT
|
3070
|
North Shore Elementary
|
Post Occupancy
|
100%
|
Song and Associates
|
Ajax
|
$32,264,250
|
$28,914,210
|
1/19/2007
|
7/19/2008
|
Post occupancy and warranty phase
|
|
C-91080
|
Renovation of stadium Facilities
|
KT
|
3035
|
Jackson, Andrew High
|
Post Occupancy
|
100%
|
Pond Junck and Walker
|
Ajax
|
$1,305,300
|
$1,214,250
|
2/6/2008
|
7/31/2008
|
Post occupancy and warranty phase
|
|
C-91130
|
New K-5
|
SR
|
3161
|
|
Construction
|
90%
|
Bhide and Hall
|
Skanska
|
$28,000,000
|
$19,987,882
|
7/9/2008
|
|
Construction proceeding
|
|
C-91140
|
New K-5
|
TG
|
3160
|
|
Design Phase III
|
0
|
Bhide and Hall
|
W.G.Mills
|
$28,000,000
|
$20,000,000
|
2/9/2009
|
|
Construction started
|
|
C91160
|
New construction to add high school wing and renovate existing Science labs, rework site for parking and access.
|
TG
|
3145
|
Darnell-Cookman Middle
|
Design Phase II
|
0
|
Harvard Jolly
|
Auld and White
|
$20,000,000
|
$16,874,000
|
12/15/2008
|
|
Design proceeding
|
|
C-91170
|
Remodel Portion of school for Arts Academy
|
AA
|
3074
|
Lake Forest Elementary
|
Post Occupancy
|
100%
|
Pond Junck & Walker
|
Auld & White
|
$1,400,000
|
$960,000
|
4/30/2008
|
|
|
|
C-91190
|
Install 16 newsecurity cameras
|
SR
|
3025
|
Kirby-Smith Middle
|
Construction
|
60%
|
John Searcy
|
Olatech
|
$151,500
|
$122,000
|
5/5/2009
|
|
Construction proceeding
|
|
C-91190
|
Install 16 new security cameras
|
SR
|
3033
|
Lee, Robert E. High
|
Construction
|
60%
|
Ohmega
|
Olatech
|
$185,000
|
$117,000
|
5/5/2009
|
|
Construction proceeding
|
|
C-91190
|
Install 16 newsecurity cameras
|
SR
|
3279
|
Kernan Middle
|
Construction
|
60%
|
Haddad
|
Olatech
|
$146,500
|
$140,000
|
5/5/2009
|
|
Construction proceeding
|
|
C-91200
|
Six classroom addition with support offices and skill lab
|
KE
|
3279
|
Kernan Middle
|
Construction
|
13%
|
VRL
|
Allstate
|
$2,000,000
|
$1,700,000
|
3/2/2009
|
|
Construction proceeding
|
|
C-91210
|
To Remodel old ISSP and current ajoined family dynamics and computer programming clasrooms into two completely separate classrooms equiped with the appropriate infrastructure to accommodate two 30 station computer labs.
|
AA
|
3086
|
Parker, Terry High
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Allstate
|
$220,000
|
$180,000
|
5/31/2008
|
|
|
|
C-91220
|
Add dividing wall to create two separate classrooms and extend existing corridor leading to existing classroom to provide access to the additional classroom.
|
AA
|
3224
|
Wolfson, Samuel W. High
|
Post Occupancy
|
100%
|
Pond Junck & Walker
|
Rivers & Rivers
|
$250,000
|
$203,500
|
6/6/2008
|
|
|
|
C-91230
|
To Design & Install a new parent pickup loop and all associated site improvements
|
AA
|
3097
|
Cedar Hills Elementary
|
Post Occupancy
|
100%
|
Bowen Civil
|
Allstate
|
$350,000
|
$295,000
|
5/21/2008
|
|
|
|
C-91250
|
Baseball & Safety Netting
|
KT
|
3223
|
Fletcher, Duncan U. High
|
Post Occupancy
|
100%
|
N/A
|
Allstate Construction
|
$180,000
|
$170,000
|
|
|
Post occupancy and warranty phase
|
|
C-91260
|
Install Fire Sprinkler system and associated egress improvements
|
KE
|
3033
|
Lee, Robert E. High
|
Construction
|
45%
|
Powell Design Group
|
Danis
|
$1,800,000
|
$1,465,000
|
12/1/2008
|
7/11/2009
|
Construction proceeding
|
|
C-91270
|
Bldg 1 fire sprinkler and rating of corridors - Design only has been funded
|
KE
|
3224
|
Wolfson, Samuel W. High
|
Design Phase III
|
0%
|
Powell Design Group
|
TBD
|
$140,000
|
$0
|
9/1/2009
|
|
Design proceeding
|
|
C-91270
|
Install Fire Sprinkler system and associated egress improvements
|
KE
|
3241
|
Forrest, Nathan Bedford High
|
Construction
|
61%
|
Powell Design Group
|
Danis
|
$2,400,000
|
$1,835,000
|
11/1/2008
|
7/11/2009
|
Construction proceeding - Admin & ROTC renov to be done in summer 09
|
|
C-91290
|
Auditorium Seating Replacement and Upgrades
|
KT
|
3237
|
Sandalwood High
|
Post Occupancy
|
100%
|
R. Dean Scott Architects, Inc.
|
Auld & White Construction
|
$1,575,000
|
$999,999
|
12/20/2008
|
7/18/2008
|
Post occupancy and warranty phase
|
|
C-91310
|
Traffic concerns
|
AA
|
3085
|
Lake Lucina Elementary
|
Post Occupancy
|
100%
|
Bowen Civil
|
Rivers
|
$350,000
|
$
|
6/30/2008
|
|
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3148
|
Brown, Richard L. Elementary
|
Construction
|
40%
|
N/A
|
ARC, Burke
|
$75,000
|
$
|
4/29/2009
|
|
Programming in progress, waiting for installation, scheduled for 4/29/09
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3082
|
Love Grove Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$49,634
|
$
|
1/26/2009
|
|
Design complete, drawings and specifications at Safety for approval. P.R. issued 10/23/08. Purchase order issued 11/21/08, ship date 1/23/09.
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3239
|
Sabal Palm Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$115,000
|
$
|
1/19/2009
|
|
Playground designed and is in Purchasing. P.O. date 10/27/08. Playground installation planned for 1/19/09. Installation complete. Safety approval 2/17/09
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3263
|
Abess Park Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$50,000
|
$
|
1/5/2009
|
|
Playground designed and is in Purchasing. P.O. date 10/27/08. Playground is installed and waiting for Safety inspection. Safety release 1/14/09
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3269
|
Biscayne
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$115,000
|
$
|
1/14/2009
|
|
Playground designed and is in Purchasing. P.O. date 10/27/08. Installation to begin 1/14/09. Safety approval 2/11/09
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3078
|
Biltmore Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$115,000
|
$
|
1/9/2009
|
|
Playground designed and is in Purchasing. P.O. date 10/27/09. Site prep ongoing. Safety approval 2/11/09. Maintenance to remove old wooden (unsafe) playground from covered play area, over the summer.
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3019
|
Upson, Ruth N. Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$7,665
|
$
|
12/1/2008
|
|
Playground designed and is on order. Complete 12/3/08
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3074
|
Lake Forest Elementary
|
Post Occupancy
|
100%
|
N/A
|
ARC/Burke
|
$5,270
|
$
|
12/1/2008
|
|
Playground designed and is on order. Complete 12/3/08
|
|
C-91320
|
To replace or add playgrounds
|
CT
|
3020
|
Fishweir Elementary
|
Pre-Planning
|
5%
|
N/A
|
|
$75,000
|
$
|
5/25/2009
|
|
Programming in progress
|
|
C-91340
|
New Parking Lot
|
KT
|
3107
|
Anderson, Douglas School of the Arts
|
Design Phase III
|
|
Edwards Engineering
|
TBD
|
$500,000
|
$460,000
|
6/8/2009
|
|
Design proceeding with Phase III. Summer '09 Construction on schedule.
|
|
C-91350
|
Correct drainage problems
|
SR
|
3235
|
Fort Caroline Elementary
|
Post Occupancy
|
100%
|
JBC
|
Coleman Young
|
$75,000
|
$72,853
|
3/16/2009
|
|
Post occupancy and warranty phase
|
|
C-91350
|
Correct drainage problems
|
SR
|
3094
|
Windy Hill Elementary
|
Design Phase III
|
2%
|
Edwards Engineering
|
|
$100,000
|
$
|
7/6/2009
|
|
Design proceeding
|
|
C-91350
|
Retention pond expansion
|
SR
|
3063
|
Fletcher, Duncan U. Middle
|
Construction
|
95%
|
JBC
|
Perry McCall
|
$175,000
|
$123,000
|
4/10/2009
|
|
Substantially complete, punchlist started
|
|
C-91350
|
Correct drainage problems - entire site
|
KE
|
3252
|
Alden Road Exceptional Child Center
|
Construction
|
20%
|
JBC
|
Rivers & Rivers
|
$150,000
|
$110,000
|
8/21/2009
|
8/21/2009
|
Construction proceeding - paving and some drainage held for summer 09
|
|
C-91350
|
Correct Drainage Problems - front of school
|
SR
|
3235
|
Fort Caroline Elementary
|
Design Phase III
|
|
JBC
|
|
$30,000
|
$
|
|
|
Design proceeding
|
|
C-91360
|
Remodel Room # 605 into Toddler Daycare
|
TG
|
3285
|
Randolph, A. Philip Academies of Technology
|
Design Phase II
|
0%
|
Design Works
|
Perry McCall
|
$250,000
|
$185,000
|
2/1/2009
|
|
Phase II Design due in January
|
|
E-99300
|
Upgrade HVAC at 10 schools
|
SR
|
DW
|
DISTRICT WIDE
|
Construction
|
99%
|
N/A
|
AC General
|
$100,000
|
$100,000
|
1/28/2008
|
|
Project completed - waiting on close outs, still waiting…3-15-09
|
|
F-10086
|
Design & Install Hurricane Shutters
|
AA
|
3256
|
Landmark Middle
|
Post Occupancy
|
100%
|
Baker Klein Engineering
|
Kane Manufactoring Corporation
|
$268,399
|
$
|
5/15/2008
|
|
|
|
F-10086
|
Design and Construction of wind and debris protection for various building envelope openings School No. : 3263, 3264, 3256, 3239, 3258, 3251
|
AA
|
3239
|
Sabal Palm Elementary
|
Post Occupancy
|
100
|
Baker Klien Engineering
|
Phoenix Architectural Products
|
$65,574
|
$
|
3/1/2008
|
|
|
|
F-10086
|
Design & Install Hurricane Shutters
|
AA
|
3251
|
Twin Lakes Academy Elementary
|
Post Occupancy
|
100
|
Baker Klein Engineering
|
Kane Manufactoring Corporation
|
$82,819
|
$
|
4/16/2008
|
|
|
|
F-10086
|
Design & Install Hurricane Shutters
|
AA
|
3258
|
Mandarin Oaks Elementary
|
Post Occupancy
|
100
|
Baker Klein ngineering
|
Pheonix Architectural Products
|
$65,575
|
$
|
3/1/2008
|
|
|
|
F-10086
|
Design & Install Hurricane Shutters
|
AA
|
3264
|
Chets Creek Elementary
|
Post Occupancy
|
100
|
Baker Klein
|
Kane Manufacturing
|
$82,819
|
$
|
4/16/2008
|
|
|
|
F-10086
|
Design & Install Hurricane Shutters
|
AA
|
3263
|
Abess Park Elementary
|
Post Occupancy
|
100
|
Baker Klein ngineering
|
Kane Manufacturing Corporation
|
$82,819
|
$
|
4/16/2008
|
|
|
|
F-10364
|
Design & Install Hurricane Protection
|
AA
|
3267
|
LaVilla School of the Arts
|
Design Phase I
|
|
Baker Klein Engineering
|
AJAX
|
$123,009
|
$
|
9/1/2009
|
|
|
|
F-48543
|
Design & Install Hurricane Protection
|
AA
|
3260
|
Mandarin High
|
Bidding
|
|
Baker Klein Engineering
|
AJAX
|
$285,942
|
$
|
7/1/2009
|
|
|
|
F-48543
|
Design & Install Hurricane Protection
|
AA
|
3232
|
Chimney Lakes Elementary
|
Bidding
|
|
Baker Klein Engineering
|
AJAX
|
$141,102
|
$
|
7/1/2009
|
|
|
|
F-48556
|
Install Special Needs generator designed by others.
|
AA
|
3062
|
Oceanway Middle
|
Construction
|
100%
|
|
Bracey
|
$41,250
|
$
|
12/1/2008
|
|
|
|
F-48556
|
Install Special Needs generator designed by others.
|
AA
|
3251
|
Twin Lakes Academy Elementary
|
Construction
|
100%
|
|
Bracey Building Contractors
|
$35,141
|
$
|
12/1/2008
|
|
|
|
M-80050
|
Install Baseball Field at Highlands Middle School #244.
|
JP
|
3244
|
Highlands Middle
|
Post Occupancy
|
|
BHR
|
TBD
|
$150,000
|
$0
|
|
2/28/2006
|
Project completed
|
|
M-80050
|
Tennis Court Complex at Baldwin Middle / High School #38
|
JP
|
3038
|
Baldwin Middle-Senior High
|
Design Phase I
|
|
BHR
|
TBD
|
$75,000
|
$75,000
|
|
|
Project completed
|
|
M-80210
|
Ktr shall safely and effectively provide termite/ treatment at DCPS facilities district wide per ITB-002-04/CP.
|
GR
|
DW
|
DISTRICT WIDE
|
Construction
|
|
n/a
|
McCall Service Inc.
|
$385,000
|
$
|
|
|
The kt was awarded October 03 with the terms of 1 year and 4 renewals at 1 year.
|
|
M-81510
|
HVAC -related facility improvements
|
GR
|
DW
|
DISTRICT WIDE
|
Construction
|
|
n/a
|
Various
|
$
|
$
|
|
|
The kt was awarded December 06 with the terms of 1 year and 4 renewals at 1year
|
|
M-84390
|
Correct drainage issues between behind original school building
|
SR
|
3229
|
Jacksonville Heights Elementary
|
Construction
|
2%
|
Bowen Eng.
|
|
$300,000
|
$
|
6/15/2009
|
|
Substantially complete, punchlist started
|
|
M-84500
|
Replace original heat pumps, air handlers and controls
|
AA
|
3257
|
Alimacani Elementary
|
Construction
|
10%
|
TLC Engineering
|
W.W. Gay
|
$424,950
|
$350,750
|
3/1/2009
|
|
|
|
M-84500
|
Replace original heat pumps, air handlers & controls
|
AA
|
3258
|
Mandarin Oaks Elementary
|
Construction
|
10%
|
TLC Engineering
|
W.W. Gay
|
$375,050
|
$294,345
|
3/1/2009
|
|
|
|
M-84510
|
Ceiling and Lighting Replacement in Corridors
|
KT
|
3237
|
Sandalwood High
|
Bidding
|
0%
|
R. Dean Scott Architects
|
Auld & White
|
$500,000
|
$460,000
|
6/8/2009
|
|
Design proceeding with Phase III to be complete by 4/20. Summer '09 Construction on schedule.
|
|
M-84520
|
Bathroom Replacement
|
KT
|
3244
|
Highlands Middle
|
Bidding
|
|
PDG
|
Auld & White
|
$600,000
|
$560,000
|
6/8/2009
|
|
Design proceeding with Phase III complete by 4/9. Summer '09 Construction on schedule.
|
|
M-84530
|
Remodel Restrooms
|
KT
|
3219
|
Stilwell, Joseph Middle
|
Bidding
|
|
Bhide & Hall Architects
|
WGMills
|
$500,000
|
$460,000
|
6/8/2009
|
|
Design proceeding with Phase III to be complete by 4/20. Summer '09 Construction on schedule.
|
|
M-84540
|
Lighting Upgrade
|
KT
|
3262
|
Robinson, Andrew Elementary
|
Construction
|
0%
|
Haddad Engineering
|
AEC
|
$100,000
|
$85,000
|
4/15/2009
|
6/26/2009
|
Construction start 4/13/09. Summer '09 Construction on schedule.
|
|
M-84540
|
Lighting Upgrade
|
KT
|
3249
|
Greenland Pines Elementary
|
Construction
|
0%
|
Haddad Engineering
|
AEC
|
$100,000
|
$85,000
|
4/15/2009
|
6/26/2009
|
Construction start 4/13/09. Summer '09 Construction on schedule.
|
|
M-84570
|
Replace bad sewer line on Bldg. 4 rm 124 restroom
|
AA
|
3230
|
Beauclerc Elementary
|
Post Occupancy
|
100%
|
Almond Engineering
|
Favor Plumbing
|
$33,880
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Plumbing Fixture Upgrade - Replace floor urinals boys r.r. bldg 4 rm 41A gym & rm 29 band room
|
AA
|
3063
|
Fletcher, Duncan U. Middle
|
Construction
|
|
M.V. Cummings
|
Breaking Ground
|
$100,000
|
$96,000
|
6/20/2009
|
|
|
|
M-84570
|
Replace 200 ft. of 8" sewer line in front of school
|
AA
|
3228
|
Merrill Road Elementary
|
Post Occupancy
|
100%
|
N/A
|
Favor Plumbing
|
$35,000
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Replace all toilet floor flanges throughout school
|
AA
|
3260
|
Mandarin High
|
Post Occupancy
|
100%
|
N/A
|
Favor Plumbing
|
$11,500
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Plumbing Fixture Upgrade & Repiping - Band bldg plumbing upgrade & domestic water repipe
|
AA
|
3031
|
Landon Middle
|
Construction
|
|
Paryiani
|
Favor Plumbing
|
$54,600
|
$
|
7/1/2009
|
|
|
|
M-84570
|
Replace cast iron drain lines in kitchen from all fixtures to grease
|
AA
|
3219
|
Stilwell, Joseph Middle
|
Construction
|
|
Bhide & Hall
|
Wg Mills
|
$49,302
|
$
|
6/20/2009
|
|
|
|
M-84570
|
Supply water line and hose bibs to courtyard.
|
AA
|
3169
|
Hull, Samuel Adams Elementary
|
Post Occupancy
|
100%
|
N/A
|
Favor Plumbing
|
$5,560
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Upgrade band room restroom and repipe dom. Water
|
AA
|
3086
|
Parker, Terry High
|
Construction
|
|
Bhide & Hall
|
Breaking Ground
|
$180,000
|
$160,000
|
6/20/2009
|
|
|
|
M-84570
|
Plumbing & Mechanical upgrades at Art Room
|
AA
|
3096
|
Ribault, Jean High
|
Construction
|
75%
|
Mcveigh & Mangum
|
Bracey
|
$34,600
|
$
|
3/27/2009
|
|
|
|
M-84570
|
Bldg. 7, replace domestic water lines.
|
AA
|
3149
|
Livingston, Smart Pope Elementary
|
Construction
|
75%
|
M.V. Cummings
|
Favor Plumbing
|
$40,000
|
$
|
6/20/2009
|
|
|
|
M-84570
|
Replace sewer line from building to Street
|
AA
|
3006
|
Rutherford, Mattie V. Alternative Education Center
|
Post Occupancy
|
100%
|
Almond
|
C&C
|
$29,200
|
$
|
3/27/2009
|
|
|
|
M-84570
|
Increase water service to school from 1-1/2" to 2"
|
AA
|
3227
|
Mayport Elementary
|
Post Occupancy
|
100%
|
N/A
|
Favor Plumbing
|
$14,000
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Replace all toilet floor flanges throughout school
|
AA
|
3224
|
Wolfson, Samuel W. High
|
Post Occupancy
|
100%
|
N/A
|
Comfort Plumbing
|
$13,000
|
$
|
11/1/2008
|
|
|
|
M-84570
|
Bldg 1 and 2 Replace 200 ft. of 6" sewer line Replace 100' of 4" sewer line from Café/Auditorium to manhole
|
AA
|
3083
|
San Jose Elementary
|
Construction
|
|
Almond Engineering
|
Favor Plumbing
|
$35,000
|
$
|
6/7/2009
|
|
|
|
M-84570
|
Lift Station Rehabilitation (Please coordinate with Maintenance)
|
AA
|
3094
|
Windy Hill Elementary
|
Construction
|
|
Almond Engineering
|
Campbell & Weeks
|
$35,000
|
$
|
6/20/2009
|
|
|
|
M-84590
|
Replacement of existing Plumbing throughout entire school
|
TG
|
3030
|
Loretto Elementary
|
Pre-Planning
|
|
TTV
|
W.G.Mills
|
$300,000
|
$237,000
|
3/15/2009
|
|
Design proceeding
|
|
M-84590
|
Replacement of existing Plumbing throughout entire school
|
TG
|
3093
|
Pinedale Elementary
|
Pre-Planning
|
|
VRL
|
Breaking Ground
|
$350,000
|
$269,000
|
3/15/2009
|
|
Design proceeding
|
|
M-84600
|
Replace Chiller
|
AA
|
3247
|
Finegan, Joseph Elementary
|
Post Occupancy
|
100%
|
Mcveigh & Mangum
|
Breaking Ground
|
$150,000
|
$
|
3/27/2009
|
|
|
|
M-84600
|
Replace Chiller
|
AA
|
3246
|
Neptune Beach Elementary
|
Post Occupancy
|
100%
|
Mcveigh & Mangum
|
Breaking Ground
|
$150,000
|
$
|
3/27/2009
|
|
|
|
M-84600
|
Replace Chiller
|
AA
|
3236
|
Jones, Mamie Agnes Elementary
|
Post Occupancy
|
100%
|
Mcveigh & Mangum
|
PPI
|
$180,000
|
$
|
3/27/2009
|
|
|
|
M-84600
|
Replace Chiller
|
AA
|
3018
|
Central Riverside Elementary
|
Post Occupancy
|
100%
|
Mcveigh & Mangum
|
PPI
|
$125,000
|
$
|
3/27/2009
|
|
|
|
M-84610
|
Install poles & fixtures
|
AA
|
3224
|
Wolfson, Samuel W. High
|
Bidding
|
|
John Searcy & Associates
|
AEC
|
$32,500
|
$
|
6/7/2009
|
|
needs construction funding 50K
|
|
M-84610
|
Install poles & fixtures
|
AA
|
3223
|
Fletcher, Duncan U. High
|
Construction
|
|
John Searcy & Associates
|
AEC
|
$32,500
|
$
|
6/7/2009
|
|
|
|
M-84610
|
Install poles and fixtures
|
AA
|
3237
|
Sandalwood High
|
Construction
|
|
John Searcy & Associates
|
KLG Electric
|
$48,773
|
$
|
6/7/2008
|
|
|
|
M-84610
|
Install poles and fixtures
|
AA
|
3265
|
First Coast High
|
Post Occupancy
|
100%
|
N/A
|
AEC Electrical
|
$17,200
|
$
|
10/2/2008
|
|
|
|
M-84610
|
Install additional poles and light fixtures
|
AA
|
3260
|
Mandarin High
|
Post Occupancy
|
100%
|
AEC Electrical
|
AEC Electrical
|
$28,750
|
$
|
10/2/2008
|
|
50K > Contractor
|
|
M-84610
|
Installation of concrete poles and lighting fixtures at the rear parking lot.
|
AA
|
3153
|
Stanton College Preparatory School
|
Post Occupancy
|
100%
|
N/A
|
AEC Electrical
|
$29,000
|
$
|
10/1/2008
|
|
50K > Contractor
|
|
M-84660
|
|
AA
|
3010
|
Lackawanna Alternative Center
|
Construction
|
95%
|
Various
|
Various
|
$200,000
|
$
|
8/1/2008
|
|
|
|
M-84690
|
Replace Generator
|
SR
|
3124
|
Evans, Saint Clair Academy
|
Post Occupancy
|
100%
|
N/A
|
AEC Electrical
|
$50,000
|
$44,000
|
12/1/2008
|
|
Post occupancy and warranty phase
|
|
M-84690
|
Replace Generator
|
SR
|
3247
|
Finegan, Joseph Elementary
|
Construction
|
|
N/A
|
AEC Electrical
|
$55,000
|
$
|
8/31/2009
|
|
Construction started
|
|
M-84690
|
Replace Generator
|
SR
|
3227
|
Mayport Elementary
|
Construction
|
95%
|
Ohmega
|
AEC Electrical
|
$55,000
|
$55,000
|
6/6/2009
|
|
Construction started
|
|
M-84690
|
Replace Generator
|
SR
|
3226
|
Crystal Springs Elementary
|
Post Occupancy
|
100%
|
N/A
|
AEC Electrical
|
$50,000
|
$44,000
|
12/8/2008
|
|
Post occupancy and warranty phase
|
|
M-84690
|
Emergency Generator Replacement, Repair and Upgrade
|
SR
|
3067
|
Technical High Administration
|
Post Occupancy
|
100%
|
Searcy
|
AEC Electrical
|
$65,000
|
$60,000
|
|
|
Post occupancy and warranty phase
|
|
M-84710
|
Castiron replacement schoolwide
|
AA
|
3075
|
Paxon Advanced
|
Post Occupancy
|
100%
|
M.V. Cummings
|
All State
|
$1,000,000
|
$820,000
|
5/31/2008
|
|
CM selected, contract negotiation started
|
|
M-84710
|
Cast Iron replacement and associated restroom renovaitons at the auditorium & art room
|
AA
|
3075
|
Paxon Advanced
|
Construction
|
100%
|
M.V. Cummings
|
Various
|
$250,000
|
$
|
12/1/2008
|
|
|
|
M-84720
|
Replace seating and correct ADA and Code issues
|
KE
|
3241
|
Forrest, Nathan Bedford High
|
Post Occupancy
|
100%
|
Powell Design Group
|
Auld & White
|
$1,000,000
|
$860,000
|
9/8/2008
|
12/31/2009
|
Post occupancy and warranty phase
|
|
M-84730
|
Design & Installation of door closers where necessary
|
AA
|
3203
|
Kings Trail Elementary
|
Post Occupancy
|
100
|
Bhide & Hall
|
Rivers & Rivers
|
$30,000
|
$25,500
|
6/15/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3020
|
Fishweir Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$15,900
|
$
|
6/16/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3045
|
Dinsmore Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$13,500
|
$
|
5/15/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3069
|
Lake Shore Middle
|
Post Occupancy
|
100
|
N/A
|
Auld & White
|
$5,320
|
$
|
6/15/2008
|
|
|
|
M-84730
|
Design & Installation of door closers where necessary
|
AA
|
3124
|
Evans, Saint Clair Academy
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Rivers & Rivers
|
$30,000
|
$25,500
|
3/5/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3016
|
Ortega Elementary
|
Post Occupancy
|
100
|
N/A
|
Auld & White
|
$18,000
|
$
|
6/16/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3085
|
Lake Lucina Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$16,000
|
$
|
4/8/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3079
|
Ramona Blvd. Elementary
|
Post Occupancy
|
100
|
N/A
|
Auld & White
|
$8,500
|
$
|
6/15/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3149
|
Livingston, Smart Pope Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$9,000
|
$
|
7/8/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3241
|
Forrest, Nathan Bedford High
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$39,400
|
$
|
6/15/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3216
|
Davis, Jefferson Middle
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$3,920
|
$
|
4/8/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3170
|
Palm Avenue Exceptional Child Center
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$3,400
|
$
|
4/8/2008
|
|
|
|
M-84730
|
Design & Install door closers/hardware
|
AA
|
3205
|
Pickett Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$14,040
|
$
|
6/15/2008
|
|
|
|
M-84730
|
Design & Installation of door closers where necessary
|
AA
|
3091
|
Mathis, Sallye B. Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Rivers & Rivers
|
$30,000
|
$25,500
|
3/28/2008
|
|
|
|
M-84740
|
Ft. Caroline Middle School No. 238
|
DH
|
3238
|
Fort Caroline Middle
|
Design Phase II
|
0
|
Akel, Logan, Shafer
|
TBD
|
$1,010,308
|
$
|
5/15/2008
|
|
Design proceeding, Phase III scheduled for April Board
|
|
M-84740
|
Beauclerc Elementary School No. 230
|
DH
|
3230
|
Beauclerc Elementary
|
Design Phase III
|
0
|
Akel, Logan ,Shafer
|
TBD
|
$1,093,992
|
$
|
5/15/2008
|
|
Design proceeding, Phase III scheduled for April Board
|
|
M-84750
|
Upgrade electrical panels in buldings 500 and 700 and add additional circuits to class rooms.
|
SR
|
3158
|
Carver, George Washington Elementary
|
Construction
|
70%
|
John Searcy and assoc.
|
KLG electric
|
$50,000
|
$45,000
|
3/10/2009
|
|
Construction started
|
|
M-84750
|
Replace main switch gear in main office
|
SR
|
3116
|
Tillis, Sadie T. Elementary
|
Construction
|
99%
|
John Searcy & Associates
|
Quality Electric
|
$37,300
|
$30,000
|
6/20/2008
|
|
Project completed - waiting on close outs
|
|
M-84750
|
Replace and consolidate main panels and sub feeds in room 126, electrical room.
|
SR
|
3038
|
Baldwin Middle-Senior High
|
Construction
|
90%
|
Ohmega Group
|
Quality Electric
|
$75,000
|
$
|
6/15/2009
|
|
Construction proceeding - added transformer replacement to be done first week school is out.
|
|
M-84750
|
Install additional panel for added capacity
|
SR
|
3165
|
Raines, William High
|
Construction
|
50%
|
McCullar Boatwright
|
KLG Electrical
|
$30,000
|
$
|
6/15/2009
|
|
Design proceeding
|
|
M-84750
|
Change out 1200 amp fused disconnect to chillers
|
SR
|
3031
|
Landon Middle
|
Construction
|
80%
|
N/A
|
KLG Electric
|
$25,000
|
$23,000
|
5/22/2009
|
|
Construction started
|
|
M-84760
|
New water service to band room and gym lobby. Repipe domestic water.
|
AA
|
3063
|
Fletcher, Duncan U. Middle
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$46,000
|
$
|
4/1/2008
|
|
|
|
M-84760
|
Bldg 4 Replace Sewer to manhole
|
AA
|
3149
|
Livingston, Smart Pope Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Allstate Construction
|
$50,000
|
$39,900
|
5/1/2008
|
|
|
|
M-84760
|
Building 2 Repipe domestic water lines, Building 1 change wall mount toilets to floor mount
|
AA
|
3205
|
Pickett Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Rivers & Rivers
|
$200,000
|
$167,000
|
6/4/2008
|
|
|
|
M-84760
|
"Upgrade restrooms-repipe domestic water lines
and new water service to music bldg." Replace 100 ft of 4" sewer line to Tech Bldg. Replace sanitary & water lines at boys locker room
|
AA
|
3090
|
Englewood High
|
Construction
|
|
Almond
|
Breaking Ground
|
$368,600
|
$360,000
|
6/20/2009
|
|
|
|
M-84760
|
Bldg 2, Replace Water lines & fixtures
|
AA
|
3048
|
Jefferson, Thomas
|
Bidding
|
|
M.V. Cummings
|
Breaking Ground
|
$80,000
|
$
|
6/20/2009
|
|
|
|
M-84760
|
Replace Cast Iron piping 2nd floor
|
AA
|
3152
|
Johnson, James Weldon Middle
|
Bidding
|
|
M.V. Cummings
|
Allstate
|
$300,000
|
$
|
6/20/2009
|
|
|
|
M-84760
|
Building 2, Replace drain lines from classrooms and main drain
|
AA
|
3078
|
Biltmore Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$85,000
|
$31,800
|
4/1/2008
|
|
|
|
M-84760
|
Plumbing Fixture Upgrade - Replace floor urinals boys r.r. bldg 4 rm 41A gym & rm 29 band room
|
AA
|
3063
|
Fletcher, Duncan U. Middle
|
Bidding
|
|
M.V. Cummings
|
Breaking Ground
|
$60,000
|
$
|
6/20/2009
|
|
|
|
M-84760
|
Domestic Water Repipe Building 7
|
AA
|
3149
|
Livingston, Smart Pope Elementary
|
Construction
|
|
M.V. Cummings
|
Favor Plumbing
|
$40,000
|
$
|
6/20/2009
|
|
|
|
M-84760
|
Relocate sewer manhole and 100'-8" Sewer Line
|
AA
|
3247
|
Finegan, Joseph Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$44,000
|
$
|
5/1/2008
|
|
|
|
M-84760
|
Bldg1, Replace Water lines & Plumbing Fixtures
|
AA
|
3084
|
Bayview Elementary
|
Construction
|
5%
|
M.V. Cummings
|
Allstate
|
$195,000
|
$186,000
|
6/20/2009
|
|
|
|
M-84760
|
Building 1, replace cast iron drain lines and renovate restrooms
|
AA
|
3068
|
Venetia Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Allstate Construction
|
$175,000
|
$147,000
|
6/15/2008
|
|
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
TG
|
3229
|
Jacksonville Heights Elementary
|
Post Occupancy
|
100%
|
Estrella Engineering
|
Batson-Cook
|
$100,000
|
$80,000
|
10/17/2008
|
|
Project completed
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
TG
|
3162
|
Daniels, Roosevelt V. Elementary
|
Post Occupancy
|
100%
|
Estrella Engineering
|
Stellar
|
$100,000
|
$80,000
|
12/1/228
|
|
Project completed
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
SR
|
3203
|
Kings Trail Elementary
|
Construction
|
75%
|
Estrella Engineering
|
Allstate
|
$100,000
|
$73,558
|
6/7/2009
|
|
Construction started
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
TG
|
3158
|
Carver, George Washington Elementary
|
Post Occupancy
|
100%
|
Estrella Engineering
|
Stellar
|
$100,000
|
$80,000
|
12/1/2008
|
|
Project completed
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
TG
|
3006
|
Rutherford, Mattie V. Alternative Education Center
|
Bidding
|
0
|
Estrella Engineering
|
Stellar
|
$100,000
|
$80,000
|
7/1/2009
|
|
GMP Excessive. Considering Re-Design
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
TG
|
3092
|
Paxon Middle
|
Post Occupancy
|
100%
|
Estrella Engineering
|
Batson-Cook
|
$100,000
|
$80,000
|
12/1/2008
|
|
Project completed
|
|
M-84770
|
Replace kitchen hood with new Code compliant hood.
|
SR
|
3094
|
Windy Hill Elementary
|
Construction
|
2%
|
Haddad Eng
|
Allstate
|
$
|
$
|
8/3/2009
|
|
CM selected, contract negotiation started
|
|
M-84780
|
Remove Cracked Concrete Ballcourt and Replace
|
TG
|
3256
|
Landmark Middle
|
Post Occupancy
|
95%
|
Baker-Klein Engineering
|
Allstate
|
$120,000
|
$
|
3/29/2008
|
|
Project completed
|
|
M-84790
|
Replace Fire Alarm Panel and Devices
|
SR
|
3116
|
Tillis, Sadie T. Elementary
|
Post Occupancy
|
100%
|
Haddad Engineering
|
Allstate
|
$320,000
|
$
|
5/15/2008
|
|
Post occupancy and warranty phase
|
|
M-84820
|
Replace windows all buildings
|
SR
|
3207
|
Stuart, J.E.B. Middle
|
Construction
|
70%
|
Pond, Junck and Walker
|
Rivers and Rivers
|
$616,000
|
$538,000
|
6/7/2009
|
|
Construction started
|
|
M-84820
|
Replace windows at bldg's 1, 3, 4 and 5
|
SR
|
3066
|
duPont, Alfred I. Middle
|
Construction
|
90%
|
Pond
|
Perry McCall
|
$313,500
|
$258,000
|
6/5/2009
|
|
Construction started
|
|
M-84820
|
Replace windows bldg's 3, 4 and 5
|
SR
|
3153
|
Stanton College Preparatory School
|
Construction
|
99%
|
Pond
|
CC Borden
|
$421,400
|
$370,000
|
3/20/2009
|
|
Project completed - waiting on close outs
|
|
M-84850
|
Parking lot repair and re-surface
|
SR
|
3064
|
Hogan-Spring Glen Elementary
|
Construction
|
75%
|
Almond
|
CC Borden
|
$125,000
|
$100,000
|
6/8/2009
|
|
Construction started
|
|
M-84850
|
Correct drainage issues east side of school
|
SR
|
3270
|
Oceanway Elementary
|
Construction
|
2%
|
Almond Engineering
|
Coleman Young
|
$50,000
|
$42,390
|
6/7/2009
|
|
Construction started
|
|
M-84850
|
Improve drainage at resource center building
|
SR
|
3096
|
Ribault, Jean High
|
Post Occupancy
|
100%
|
Bowen
|
Coleman Young
|
$90,000
|
$66,274
|
3/1/2009
|
|
Post occupancy and warranty phase
|
|
M-84850
|
Improve drainage
|
SR
|
3214
|
Hyde Grove Elementary
|
Construction
|
99%
|
Almond
|
Olatech
|
$53,000
|
$22,500
|
3/27/2009
|
|
Project completed - waiting on close outs
|
|
M-84880
|
Replace Intercom System
|
SR
|
3006
|
Rutherford, Mattie V. Alternative Education Center
|
Construction
|
70%
|
Haddad
|
Thompson Electric
|
$134,000
|
$58,000
|
6/7/2009
|
|
Construction proceeding
|
|
M-84880
|
Replace Security Alarm System
|
SR
|
3019
|
Upson, Ruth N. Elementary
|
Design Phase I
|
|
Searcy Engineering
|
|
$134,500
|
$120,000
|
|
|
Design Phase started
|
|
M-84880
|
Repalce Fire Alarm System
|
SR
|
3073
|
Love, John Elementary
|
Construction
|
99%
|
Searcy and Associates
|
Auld and White
|
$260,000
|
$185,500
|
2/17/2009
|
|
Project completed - waiting on close outs.
|
|
M-84880
|
Replace Security Alarm System
|
SR
|
3154
|
Ford, John E. Elementary
|
Design Phase I
|
|
Searcy Engineering
|
|
$134,500
|
$120,000
|
|
|
Design Phase started
|
|
M-84880
|
Replace fire alarm
|
SR
|
3066
|
duPont, Alfred I. Middle
|
Post Occupancy
|
99%
|
OHMEGA
|
Auld and White
|
$400,340
|
$349,340
|
7/1/2008
|
|
Post occupancy and warranty phase
|
|
M-84880
|
Replace Fire Alarm System
|
SR
|
3068
|
Venetia Elementary
|
Construction
|
90%
|
OHMEGA
|
AEC Electrical
|
$315,000
|
$156,500
|
3/30/2009
|
|
Construction proceeding
|
|
M-84880
|
Replace Intercom System
|
SR
|
3019
|
Upson, Ruth N. Elementary
|
Construction
|
70%
|
Haddad
|
Thompson Electric
|
$168,000
|
$72,000
|
6/7/2009
|
|
Construction proceeding
|
|
M-84880
|
Replace Intercom System
|
SR
|
3235
|
Fort Caroline Elementary
|
Design Phase I
|
|
Ohmega
|
|
$125,364
|
$106,000
|
|
|
Design Phase started
|
|
M-84880
|
Replace Intercom System
|
SR
|
3164
|
Mt. Herman Exceptional Child Center
|
Design Phase I
|
|
Ohmega
|
|
$122,500
|
$105,000
|
|
|
Design Phase started
|
|
M-84880
|
Replace Intercom System
|
SR
|
3233
|
Lone Star Elementary
|
Design Phase I
|
|
Ohmega
|
|
$122,500
|
$105,000
|
|
|
Design Phase started
|
|
M-84880
|
Replace Intercom System
|
SR
|
3094
|
Windy Hill Elementary
|
Construction
|
70%
|
Haddad
|
Thompson Electric
|
$110,000
|
$92,000
|
6/7/2009
|
|
Construction proceeding
|
|
M-84890
|
Atlantic Beach Elementary No. 65
|
DH
|
3065
|
Atlantic Beach Elementary
|
Construction
|
15
|
Akel ,Logan, Shafer
|
BBG
|
$131,817
|
$
|
11/1/2007
|
|
Construction started, Part of a 6 school package
|
|
M-84890
|
John E. Ford Elementary No. 154
|
DH
|
3154
|
Ford, John E. Elementary
|
Construction
|
30
|
Akel, Logan, Shafer PA
|
Advanced Roofing
|
$986,514
|
$785,000
|
9/1/2007
|
|
Construction started
|
|
M-84890
|
Palm Ave Exceptional No. 170
|
DH
|
3170
|
Palm Avenue Exceptional Child Center
|
Construction
|
15
|
Akel, Logan, Shafer
|
BBG
|
$53,625
|
$
|
11/1/2007
|
|
Construction proceeding, Part of a 6 school package
|
|
M-84890
|
Mayport Elementary School No. 227
|
DH
|
3227
|
Mayport Elementary
|
Construction
|
80
|
Akel, Logan, Shafer
|
BBG
|
$33,727
|
$
|
11/1/2007
|
|
Construction proceeding, Part of a 6 school package
|
|
M-84890
|
Lone Star Elementary No. 233
|
DH
|
3233
|
Lone Star Elementary
|
Construction
|
95
|
Akel Logan Shafer
|
BBG
|
$87,796
|
$
|
11/1/2007
|
|
Construction proceeding, Part of a 6 school package
|
|
M-84890
|
Urban Resource Center No 275
|
DH
|
3275
|
Urban Resource Center
|
Bidding
|
95
|
Akel, Logan, Shafer
|
BBG
|
$146,770
|
$
|
11/1/2007
|
|
Construction proceeding, Part of a 6 school package
|
|
M-84890
|
Alden Road Exceptional No. 252
|
DH
|
3252
|
Alden Road Exceptional Child Center
|
Construction
|
40
|
Akel,Logan,Shafer
|
BBG
|
$333,058
|
$
|
11/1/2007
|
|
Construction proceeding
|
|
M-84920
|
Design & Install door closers/hardware
|
AA
|
3236
|
Jones, Mamie Agnes Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$22,000
|
$
|
4/8/2008
|
|
|
|
M-84920
|
Design & Install door closers/hardware
|
AA
|
3098
|
Timucuan Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$15,800
|
$
|
4/8/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3170
|
Palm Avenue Exceptional Child Center
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Auld & White
|
$21,720
|
$
|
7/8/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3153
|
Stanton College Preparatory School
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Auld & White
|
$29,400
|
$
|
7/8/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3091
|
Mathis, Sallye B. Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
TBD
|
$12,750
|
$21,250
|
7/5/2008
|
|
|
|
M-84920
|
Design & Install door closers/hardware
|
AA
|
3213
|
Arlington Middle
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$21,000
|
$
|
7/8/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3083
|
San Jose Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Stellar
|
$214,225
|
$
|
7/12/2008
|
|
|
|
M-84920
|
Various Hardware and Door Access Replacement
|
AA
|
3228
|
Merrill Road Elementary
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$90,000
|
$
|
6/20/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3267
|
LaVilla School of the Arts
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Auld & White
|
$6,240
|
$
|
7/18/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3208
|
Parkwood Heights Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Allstate
|
$82,561
|
$
|
5/13/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3015
|
Brentwood Elementary
|
Post Occupancy
|
100
|
Bhide & Hall
|
Rivers & Rivers
|
$31,300
|
$
|
4/1/2007
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3059
|
Garden City Elementary
|
Construction
|
0
|
Bhide & Hall
|
Olatech Group
|
$45,000
|
$
|
6/6/2009
|
|
|
|
M-84920
|
Install Door Closers & Door Magnets
|
AA
|
3001
|
Central Administration Building
|
Post Occupancy
|
100%
|
N/A
|
Auld & White
|
$21,400
|
$
|
6/15/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3086
|
Parker, Terry High
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Allstate
|
$266,331
|
$
|
5/13/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3084
|
Bayview Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Allstate
|
$53,775
|
$
|
5/13/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3073
|
Love, John Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Allstate
|
$65,000
|
$
|
5/13/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3224
|
Wolfson, Samuel W. High
|
Post Occupancy
|
100%
|
Bhide & Hall
|
Auld & White
|
$21,200
|
$
|
7/6/2008
|
|
|
|
M-84920
|
Design & Install Doors and Door Hardware
|
AA
|
3077
|
Hyde Park Elementary
|
Construction
|
100%
|
Bhide & Hall
|
Olatech
|
$52,000
|
$
|
7/12/2008
|
|
|
|
M-84960
|
Egress improvements, window replacement, CR improvements
|
KE
|
3164
|
Mt. Herman Exceptional Child Center
|
Construction
|
99%
|
Design Works
|
Auld & White
|
$1,825,000
|
$1,360,000
|
12/17/2007
|
|
Pending final inspection - tied to sprinkler project
|
|
M-84960
|
Canopy, bus loop & parent loop
|
KE
|
3252
|
Alden Road Exceptional Child Center
|
Construction
|
90%
|
Dsign Works
|
Rivers
|
$1,800,302
|
$894,000
|
8/1/2007
|
2/15/2008
|
Construction on Hold - paving and canopy to be complete Summer 09
|
|
M-84960
|
|
AA
|
3265
|
First Coast High
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$27,640
|
$22,400
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3213
|
Arlington Middle
|
Post Occupancy
|
100%
|
Bhide Hall
|
C.C. Borden
|
$47,160
|
$17,200
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3252
|
Alden Road Exceptional Child Center
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$2,950
|
$11,700
|
12/17/2007
|
|
|
|
M-84960
|
Fire Sprinklers
|
KE
|
3164
|
Mt. Herman Exceptional Child Center
|
Construction
|
98%
|
Powell Design Group
|
Fire Fighters
|
$200,000
|
$200,000
|
7/9/2008
|
|
Final painting of pipe in progress
|
|
M-84960
|
|
AA
|
3086
|
Parker, Terry High
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$47,160
|
$22,200
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3149
|
Livingston, Smart Pope Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$47,384
|
$41,400
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3066
|
duPont, Alfred I. Middle
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$45,720
|
$41,600
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3209
|
Holiday Hill Elementary
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$55,480
|
$49,000
|
12/17/2007
|
|
|
|
M-84960
|
|
AA
|
3092
|
Paxon Middle
|
Post Occupancy
|
100%
|
Bhide & Hall
|
C.C. Borden
|
$63,780
|
$56,400
|
12/17/2007
|
|
|
|
M-85300
|
Replace Kitchen Hood with New Code Compliant Hood
|
TG
|
3169
|
Hull, Samuel Adams Elementary
|
Post Occupancy
|
100%
|
MV Cummings
|
Batson-Cook
|
$41,950
|
$35,875
|
12/1/2008
|
|
Project completed
|
|
M-85310
|
Replace HVAC equipment, piping, insulation and controls
|
TG
|
3285
|
Randolph, A. Philip Academies of Technology
|
Construction
|
85%
|
Paryani Engineers
|
AC General
|
$3,000,000
|
$2,645,000
|
6/1/2007
|
|
Phase I Work Complete
|
|
M-85310
|
Replace HVAC Air Handlers and Piping
|
TG
|
3285
|
Randolph, A. Philip Academies of Technology
|
Design Phase II
|
|
Paryani Engineers, Inc
|
TBD
|
$500,000
|
$405,000
|
2/1/2009
|
|
Design proceeding
|
|
M-85360
|
Upgrade security alarm system
|
SR
|
3240
|
Arlington Heights Elementary
|
Construction
|
90%
|
Haddad
|
AEC Electrical
|
$150,000
|
$93,240
|
4/6/2009
|
|
Construction proceeding
|
|
M-85360
|
Updating card readers, door contacts, access panels and power supplies at School # 149
|
SR
|
3149
|
Livingston, Smart Pope Elementary
|
Construction
|
90%
|
Haddad Engineering
|
AEC Electrical
|
$124,832
|
$120,000
|
3/23/2009
|
|
Construction started
|
|
M-85380
|
Design & Install Grease Traps
|
AA
|
3209
|
Holiday Hill Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$45,114
|
$36,779
|
|
|
|
|
M-85380
|
|
AA
|
3218
|
San Mateo Elementary
|
Bidding
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $6667tivated for design Construction Phase Unfunded, Awaiting Programming 40k needed
|
|
M-85380
|
Design & Install Grease Traps
|
AA
|
3158
|
Carver, George Washington Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Comfort Plumbing
|
$36,800
|
$
|
11/1/2008
|
|
|
|
M-85380
|
|
AA
|
3128
|
Tolbert, Susie E.
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Campbell & Weeks
|
$34,700
|
$
|
11/1/2008
|
|
|
|
M-85380
|
|
AA
|
3068
|
Venetia Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Allstate
|
$
|
$
|
6/15/2008
|
|
|
|
M-85380
|
|
AA
|
3224
|
Wolfson, Samuel W. High
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$41,870
|
$36,150
|
8/1/2008
|
|
|
|
M-85380
|
|
AA
|
3071
|
Hendricks Avenue Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$51,520
|
$
|
6/30/2008
|
|
|
|
M-85380
|
|
AA
|
3225
|
Seabreeze Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$45,338
|
$36,150
|
4/1/2008
|
|
|
|
M-85380
|
Design & Install Grease Traps
|
AA
|
3208
|
Parkwood Heights Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$49,526
|
$41,450
|
|
|
|
|
M-85380
|
Design & Install Grease Traps
|
AA
|
3206
|
Brookview Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Campbell & Weeks
|
$40,770
|
$36,150
|
11/1/2008
|
|
|
|
M-85380
|
Design & Install of Grease Traps
|
AA
|
3092
|
Paxon Middle
|
Post Occupancy
|
100
|
M.V. Cummings
|
Auld & White
|
$47,789
|
$38,150
|
3/28/2008
|
|
|
|
M-85380
|
Design & Install of Grease Traps
|
AA
|
3107
|
Anderson, Douglas School of the Arts
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$36,990
|
$
|
6/30/2008
|
|
|
|
M-85380
|
|
AA
|
3238
|
Fort Caroline Middle
|
Post Occupancy
|
100%
|
M.V. Cummings
|
TBD
|
$59,620
|
$33,750
|
8/1/2008
|
|
|
|
M-85380
|
Design & Install of Grease Traps
|
AA
|
3170
|
Palm Avenue Exceptional Child Center
|
Post Occupancy
|
100
|
M.V. Cummings
|
Rivers & Rivers
|
$37,226
|
$36,150
|
6/30/2008
|
|
|
|
M-85380
|
|
AA
|
3012
|
West Riverside Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3077
|
Hyde Park Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Traps
|
AA
|
3223
|
Fletcher, Duncan U. High
|
Post Occupancy
|
100
|
M.V. Cummings
|
Rivers & Rivers
|
$51,332
|
$36,150
|
12/17/2007
|
|
|
|
M-85380
|
|
AA
|
3097
|
Cedar Hills Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2008
|
|
Completed 07/08 as part of another project
|
|
M-85380
|
|
AA
|
3162
|
Daniels, Roosevelt V. Elementary
|
Bidding
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
7/17/2009
|
|
Design Phase started $6667 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3234
|
Jackson, Stonewall Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/9/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K
|
|
M-85380
|
Design & Install of Grease Traps
|
AA
|
3153
|
Stanton College Preparatory School
|
Post Occupancy
|
100
|
M.V. Cummings
|
Rivers & Rivers
|
$41,870
|
$36,150
|
12/19/2007
|
|
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3220
|
King, Martin Luther Jr. Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
|
AA
|
3243
|
Gregory Drive Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Comfort Plumbing
|
$42,100
|
$
|
11/1/2008
|
|
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3203
|
Kings Trail Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3233
|
Lone Star Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
|
AA
|
3064
|
Hogan-Spring Glen Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3059
|
Garden City Elementary
|
Bidding
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
7/17/2009
|
|
Design Phase started $6667 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design and Installation of new Grease Traps
|
AA
|
3046
|
Arlington Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Rivers & Rivers
|
$38,569
|
$
|
1/31/2008
|
|
|
|
M-85380
|
|
AA
|
3241
|
Forrest, Nathan Bedford High
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$36,368
|
$
|
6/30/2008
|
|
|
|
M-85380
|
|
AA
|
3014
|
Grand Park Career Center
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3045
|
Dinsmore Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings Engineers
|
Campbell & Weeks
|
$48,400
|
$
|
11/1/2008
|
|
|
|
M-85380
|
|
AA
|
3019
|
Upson, Ruth N. Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install Grease Interceptors
|
AA
|
3214
|
Hyde Grove Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
|
AA
|
3221
|
Normandy Village Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Favor Plumbing
|
$39,900
|
$
|
11/1/2008
|
|
|
|
M-85380
|
|
AA
|
3169
|
Hull, Samuel Adams Elementary
|
Bidding
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/1/2009
|
|
Design Phase started $6667 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85380
|
Design & Install of Grease Traps
|
AA
|
3065
|
Atlantic Beach Elementary
|
Post Occupancy
|
100
|
M.V. Cummings
|
Rivers & Rivers
|
$49,001
|
$3,080
|
12/13/2007
|
|
|
|
M-85380
|
|
AA
|
3215
|
Justina Road Elementary
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Auld & White
|
$41,540
|
$36,150
|
6/1/2008
|
|
|
|
M-85380
|
|
AA
|
3207
|
Stuart, J.E.B. Middle
|
Post Occupancy
|
100%
|
M.V. Cummings
|
Campbell & Weeks
|
$42,889
|
$
|
11/1/2008
|
|
|
|
M-85380
|
|
AA
|
3018
|
Central Riverside Elementary
|
Design Phase III
|
|
M.V. Cummings
|
TBD
|
$
|
$
|
6/17/2009
|
|
Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming 40K needed
|
|
M-85450
|
Roof Replacement At Various Schools
|
DH
|
3067
|
Technical High Administration
|
Construction
|
95
|
Akel, Logan, Shafer
|
BBG
|
$184,560
|
$145,572
|
6/15/2007
|
12/5/2007
|
Substantially complete, punchlist started , Final completion scheduled for april board
|
|
M-85450
|
Roof Replacement At Various Schools
|
DH
|
3002
|
Schultz Center
|
Construction
|
95
|
Akel, Logan, Shafer
|
BBG
|
$551,797
|
$437,738
|
5/9/2007
|
|
Substantially complete, punchlist started, Final completion scheduled for april board
|
|
M-85450
|
Roof Replacement At Various Schools
|
DH
|
3210
|
Oak Hill Elementary
|
Construction
|
95
|
Akel, Logan, Shafer
|
BBG
|
$761,528
|
$604,638
|
7/1/2007
|
|
Substantially complete, punchlist started, Final completion scheduled for april board
|
|
M-85450
|
Roof Replacement At Various Schools
|
DH
|
3158
|
Carver, George Washington Elementary
|
Construction
|
95
|
Akel, Logan, Shafer
|
BBG
|
$578,855
|
$457,947
|
6/25/2007
|
|
Substantially complete, punchlist started, Final completion scheduled for april board
|
|
M-85450
|
Roof Replacement At Various Schools
|
DH
|
3096
|
Ribault, Jean High
|
Construction
|
95
|
Akel, Logan, Shafer
|
BBG
|
$525,911
|
$416,161
|
7/1/2007
|
|
Substantially complete, punchlist started , Final completion scheduled for april board
|
|
M-85450
|
Roof Replacement at Various Schools
|
DH
|
3035
|
Jackson, Andrew High
|
Construction
|
99
|
Akel, Logan, Shafer
|
BBG
|
$566,785
|
$352,160
|
5/9/2007
|
|
Project completed Final inspection scheduled for march 11 2008
|
|
M-85600
|
Alimacani Elementary - New Metal Roofing - Reuse of Plans
|
DH
|
3257
|
Alimacani Elementary
|
Post Occupancy
|
100
|
Akel, Logan, Shafer
|
Childers Roofing
|
$1,648,941
|
$1,360,000
|
2/1/2007
|
|
Project completed Substantial and final scheduled for april board
|
|
M-85600
|
Sabal Palm Elementary - New Metal Roofing - Reuse of Plans
|
DH
|
3239
|
Sabal Palm Elementary
|
Construction
|
35
|
Akel, Logan, Shafer PA
|
BBG
|
$1,964,667
|
$1,625,000
|
8/1/2007
|
|
Construction proceeding
|
|
M-85600
|
Chimney Lakes Elementary - New Metal Roofing - Reuse of plans
|
DH
|
3232
|
Chimney Lakes Elementary
|
Bidding
|
100
|
Akel, Logan, Shafer
|
BBG
|
$1,648,941
|
$1,360,000
|
2/1/2007
|
8/10/2007
|
Project completed Substantial and final scheduled for April Board
|
|
M-85900
|
Replace Gamewell 400
|
SR
|
3227
|
Mayport Elementary
|
Post Occupancy
|
100%
|
Ohmega
|
AEC
|
$280,000
|
$260,000
|
4/17/2008
|
|
Post occupancy and warranty phase
|
|
M-85900
|
Replace Gamewell Flex 300
|
SR
|
3257
|
Alimacani Elementary
|
Construction
|
99%
|
Ohmega
|
Exum
|
$424,000
|
$259,000
|
4/28/2008
|
|
Project completed - waiting on close outs
|
|
M-86000
|
Rubberized track resufacing and repair
|
JP
|
DW
|
DISTRICT WIDE
|
|
|
n/a
|
All American Tracks
|
$
|
$
|
|
|
|
|
m86240
|
|
SC
|
3230
|
Beauclerc Elementary
|
Post Occupancy
|
100
|
na
|
certified
|
$75,000
|
$
|
1/15/2008
|
|
Post occupancy and warranty phase
|
|
M-87070
|
Inspection, design, and repair of all exterior bleachers district wide
|
AA
|
DW
|
DISTRICT WIDE
|
Construction
|
75%
|
Baker Klien Engineering
|
Various
|
$400,000
|
$200,000
|
12/1/2007
|
|
Some prior year funding used
|
|
M-87080
|
|
JP
|
DW
|
DISTRICT WIDE
|
|
|
|
|
$
|
$
|
|
|
Installation done in accordance with ITB-018-03/RW
|
|
M-87090
|
Restroom Upgrade
|
WA
|
3265
|
First Coast High
|
|
|
|
Auld & White
|
$
|
$
|
|
|
Project completed
|
|
M-87090
|
Restroom Upgrade
|
WA
|
3244
|
Highlands Middle
|
Post Occupancy
|
|
|
Auld & White
|
$90,617
|
$
|
|
|
Project completed
|
|
M-87090
|
Restroom Upgrade
|
WA
|
3158
|
Carver, George Washington Elementary
|
|
|
|
Southern Sisters
|
$20,910
|
$
|
|
|
Complete
|
|
M-87090
|
Restroom Upgrade
|
WA
|
3168
|
Butler, Eugene J. Middle
|
|
|
|
Southern Sisters
|
$9,223
|
$
|
|
|
Complete
|
|
M-87100
|
Renovate HVAC Systems - Second Phase
|
TG
|
3260
|
Mandarin High
|
Construction
|
90%
|
Paryani Engineers Inc
|
AC General
|
$2,500,000
|
$2,000,000
|
6/11/2008
|
|
Summer Work Complete. Change Order Work Underway
|
|
M-87100
|
Renovate HVAC Systems - Second Phase
|
TG
|
3265
|
First Coast High
|
Construction
|
99%
|
Paryani Engineers
|
AC General
|
$2,500,000
|
$2,000,000
|
6/11/2008
|
|
Summer Work Complete. Change Order Work Ongoing.
|
|
M-87540
|
Modernize elevators at 280, 285 (3 elevators)
|
GR
|
Various
|
|
Construction
|
99.9%
|
Haddad
|
Allstate
|
$125,000
|
$125,000
|
5/14/2007
|
2/1/2008
|
Project completed
|
|
M-87900
|
Roof Replacement at JEB Stuart Middle
|
DH
|
3207
|
Stuart, J.E.B. Middle
|
Post Occupancy
|
100
|
Parks Three Architecture
|
Reaves Roofing
|
$1,998,520
|
$1,592,000
|
12/15/2005
|
11/15/2006
|
Post occupancy and warranty phase
|
|
m88850
|
|
SC
|
3107
|
Anderson, Douglas School of the Arts
|
Post Occupancy
|
100
|
na
|
certified
|
$225,000
|
$
|
2/1/2008
|
|
Post occupancy and warranty phase
|
|
m88850
|
mod piping configuration, repl chiller
|
SC
|
3237
|
Sandalwood High
|
Post Occupancy
|
100
|
na
|
brooks
|
$190,000
|
$
|
2/1/2008
|
|
Post occupancy and warranty phase
|
|
m88850
|
|
SC
|
3249
|
Greenland Pines Elementary
|
Post Occupancy
|
100
|
na
|
brooks
|
$200,000
|
$
|
2/1/2008
|
|
Post occupancy and warranty phase
|
|
M-88850
|
|
SC
|
3238
|
Fort Caroline Middle
|
Design Phase I
|
10
|
TBD
|
Brooks/TBD
|
$575,000
|
$
|
6/1/2009
|
|
Program under review
|
|
M-88850
|
|
SC
|
3224
|
Wolfson, Samuel W. High
|
Design Phase I
|
10
|
TBD
|
Brooks/TBD
|
$300,000
|
$
|
6/1/2009
|
|
Program under review
|
|
M-88850
|
|
SC
|
3033
|
Lee, Robert E. High
|
Design Phase I
|
20
|
Matern
|
Certified/tbd
|
$900,000
|
$
|
11/1/2008
|
|
Construction started
|
|
M-88850
|
|
SC
|
3063
|
Fletcher, Duncan U. Middle
|
Design Phase II
|
10
|
eng
|
TBD
|
$475,000
|
$
|
6/1/2009
|
|
Program under review
|
|
M-88850
|
|
SC
|
3065
|
Atlantic Beach Elementary
|
Construction
|
25
|
na
|
JCI/Brooks
|
$150,000
|
$
|
12/15/2008
|
|
Construction started
|
|
M-88850
|
HVAC/EMCS/IAQ Improvements
|
SC
|
3241
|
Forrest, Nathan Bedford High
|
Post Occupancy
|
100
|
eng
|
jci
|
$590,000
|
$
|
3/1/2008
|
|
Post occupancy and warranty phase
|
|
M-88850
|
|
SC
|
3211
|
Southside Middle
|
Design Phase I
|
10
|
na
|
MED-HVAC
|
$50,000
|
$
|
1/1/2009
|
|
Program under review
|
|
m-88850
|
repl deteriorated vav boxes
|
SC
|
3038
|
Baldwin Middle-Senior High
|
Post Occupancy
|
100
|
na
|
brooks
|
$0
|
$
|
2/26/2008
|
|
Post occupancy and warranty phase
|
|
M-88850
|
|
SC
|
3248
|
White, Edward H. High
|
Design Phase I
|
0
|
na
|
tbd
|
$250,000
|
$
|
6/1/2009
|
|
Program under review
|
|
M-88850
|
HVAC/EMCS/IAQ Improvements
|
SC
|
3245
|
Crown Point Elementary
|
Post Occupancy
|
90
|
eng
|
jci
|
$600,000
|
$
|
2/1/2008
|
|
Punchlist progressing
|
|
M-88850
|
|
SC
|
3262
|
Robinson, Andrew Elementary
|
Design Phase I
|
10
|
na
|
brooks/jci
|
$225,000
|
$
|
3/1/2009
|
|
Program under review
|
|
M-88850
|
HVAC and Energy work
|
SC
|
3063
|
Fletcher, Duncan U. Middle
|
Post Occupancy
|
100
|
eng
|
jci
|
$300,000
|
$
|
3/15/2008
|
|
Post occupancy and warranty phase
|
|
M-88850
|
HVAC work to correct system deficiencies, iaq issues
|
SC
|
3223
|
Fletcher, Duncan U. High
|
Post Occupancy
|
100
|
eng
|
JCI
|
$600,000
|
$
|
1/1/2008
|
|
Post occupancy and warranty phase
|
|
M-88850
|
HVAC Work for maintainability
|
SC
|
3253
|
Twin Lakes Academy Middle
|
Design Phase I
|
10
|
TBD
|
TBD
|
$300,000
|
$
|
6/1/2009
|
|
Programming in progress
|
|
m-88850
|
mod piping configuration, upgrade emcs, install vfds
|
SC
|
3224
|
Wolfson, Samuel W. High
|
Post Occupancy
|
100
|
na
|
brooks
|
$125,000
|
$
|
2/1/2008
|
|
Post occupancy and warranty phase
|
|
SSF- #65
|
Install video entry system
|
SR
|
3065
|
Atlantic Beach Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electric
|
$33,000
|
$22,500
|
7/13/2009
|
|
Construction started
|
|
SSF-#154
|
Install video entry system
|
SR
|
3154
|
Ford, John E. Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electric
|
$28,000
|
$22,400
|
7/13/2009
|
|
Construction started
|
|
SSF-#225
|
Install video entry system
|
SR
|
3225
|
Seabreeze Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electrtic
|
$25,600
|
$22,400
|
7/13/2009
|
|
Construction started
|
|
SSF-#246
|
Install video entry system
|
SR
|
3246
|
Neptune Beach Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electric
|
$25,500
|
$22,400
|
7/13/2009
|
|
Construction started
|
|
SSF-#249
|
Install video entry system
|
SR
|
3249
|
Greenland Pines Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electric
|
$25,500
|
$22,400
|
7/13/2009
|
|
Construction started
|
|
SSF-#84
|
Install video entry system
|
SR
|
3089
|
Woodland Acres Elementary
|
Construction
|
2%
|
Haddad
|
Quality Electric
|
$25,500
|
$22,400
|
7/13/2009
|
|
Construction started
|