| Project | School | Phase | Budget | Construction | |||||||||
| Number | Project Description | PM | No. | Name | Current | Actual % Complete | Architect/Engineer | Contractor | Project | Const. | Start | SC Date | Comments |
| C-90470 | New K-8"DD"(K-8) | KE | 3274 | Construction | 5 | JSA | Ajax | $42,100,000 | $35,800,000 | 1/7/2008 | 6/6/2009 | Construction proceeding - bldg foundations in progress | |
| C-90640 | Phase Out/Update Portables Districtwide | BA | 3225 | Seabreeze Elementary | Construction | n/a | Allstate | $3,000,000 | $500,000 | 8/1/2005 | |||
| C-90650 | New High School Campus with Athletic Facities | TG | 3268 | "AAA" High | Design Phase III | 0% | Schenkel Shultz Architects | WG Mills | $103,625,000 | $77,050,000 | 4/1/2008 | Design proceeding | |
| C-91020 | Construction of new locker room facilites. | KT | 3280 | Peterson, Frank H. Academies of Technology | Post Occupancy | 100% | Drake/Pattillo | Allstate | $1,015,745 | $935,800 | 12/14/2006 | 8/16/2007 | Post occupancy and warranty phase |
| C-91060 | New 788 Student Station Elementary School and Master Plan for K-12 Campus | KT | 3142 | Chaffee Road -- School "B" | Post Occupancy | 100% | Tercilla - Courtemanche | Elkins | $22,140,000 | $19,220,000 | 6/21/2006 | 6/20/2007 | Post occupancy and warranty phase |
| C-91080 | Conversion of existing North Shore ES to a K-8 school | KT | 3070 | North Shore Elementary | Construction | 80% | Song and Associates | Ajax | $32,264,250 | $28,434,828 | 1/19/2007 | 7/19/2008 | Construction proceeding - Substantial for new buildings by 3/28/08. North Shore students to occupy on 4/7/08. Construction of bus loop, site work, and Andrew Jackson Athletics will continue thru 8/08. |
| C-91130 | New K-5 | TG | 3161 | Design Phase II | 0 | Bhide and Hall | Skanska | $28,000,000 | $21,765,755 | 7/9/2008 | Design proceeding | ||
| C-91130 | New K-5 | TG | 3160 | Design Phase II | 0 | Bhide and Hall | W.G.Mills | $28,000,000 | $21,765,755 | 5/9/2008 | Design proceeding | ||
| C91160 | New construction to add high school wing and renovate existing Science labs, rework site for parking and access. | TG | 3145 | Darnell-Cookman Middle | Design Phase I | 0 | Harvard Jolly | TBD | $20,000,000 | $16,874,000 | 10/15/2008 | CM selection in progress | |
| C-91170 | Remodel Portion of school for Arts Academy | AA | 3074 | Lake Forest Elementary | Construction | 10 | Pond Junck & Walker | Auld & White Construction | $1,400,000 | $960,000 | 4/30/2008 | $300K Estimated for FF&E | |
| C-91190 | Install 16 newsecurity cameras | SR | 3107 | Anderson, Douglas School of the Arts | Construction | Haddad | EXUM | $190,000 | $154,000 | 5/1/2008 | Construction started | ||
| C-91190 | Install 16 newsecurity cameras | SR | 3259 | Mandarin Middle | Construction | Haddad | EXUM | $146,000 | $123,000 | 5/18/2008 | Construction started | ||
| C-91190 | Install 16 newsecurity cameras | SR | 3025 | Kirby-Smith Middle | Construction | John Searcy | $151,500 | $122,500 | Construction on Hold for funding 08/09 | ||||
| C-91190 | Install 16 newsecurity cameras | SR | 3031 | Landon Middle | Construction | Haddad | EXUM | $141,500 | $112,500 | 4/24/2008 | Construction started | ||
| C-91190 | Install 16 newsecurity cameras | SR | 3069 | Lake Shore Middle | Construction | Haddad | EXUM | $177,000 | $144,000 | 5/12/2008 | Construction started | ||
| C-91190 | Install 16 new security cameras | SR | 3090 | Englewood High | Construction | Haddad | EXUM | $190,000 | $174,000 | 4/24/2008 | Construction started | ||
| C-91190 | Install 16 newsecurity cameras | SR | 3279 | Kernan Middle | Construction | Haddad | EXUM | $146,500 | $ | Construction on Hold for funding 08/09 | |||
| C-91190 | Install 16 newsecurity cameras | SR | 3254 | Mayport Middle | Construction | Searcy | AEC | $200,000 | $188,000 | 4/20/2008 | Construction started | ||
| C-91190 | Install 16 newsecurity cameras | SR | 3253 | Twin Lakes Academy Middle | Construction | Haddad | EXUM | $168,000 | $131,131 | 4/24/2008 | Construction started | ||
| C-91190 | nstall 16 newsecurity cameras | SR | 3146 | Gilbert, Matthew Middle | Construction | Searcy | AEC | $193,000 | $167,000 | 5/1/2008 | Construction started | ||
| C-91200 | Six classroom addition with support offices and skill lab | KE | 3279 | Kernan Middle | Pre-Planning | 0 | VRL | TBD | $2,000,000 | $1,700,000 | 9/1/2008 | A/E selected - CM selection in progress | |
| C-91210 | To Remodel old ISSP and current ajoined family dynamics and computer programming clasrooms into two completely separate classrooms equiped with the appropriate infrastructure to accommodate two 30 station computer labs. | AA | 3086 | Parker, Terry High | Construction | 0 | Bhide & Hall | Allstate | $220,000 | $180,000 | 5/31/2008 | FF&E $80,000 | |
| C-91220 | Add dividing wall to create two separate classrooms and extend existing corridor leading to existing classroom to provide access to the additional classroom. | AA | 3224 | Wolfson, Samuel W. High | Construction | 0 | Pond Junck & Walker | Rivers & Rivers | $250,000 | $203,500 | 6/6/2008 | ||
| C-91230 | To Design & Install a new parent pickup loop and all associated site improvements | AA | 3097 | Cedar Hills Elementary | Bidding | 0 | Bowen Civil | Allstate | $350,000 | $295,000 | 5/21/2008 | Awaiting GMP | |
| C-91240 | Pave Parking Lot Across McDuff From Lee HS | JW | 3033 | Lee, Robert E. High | Construction | 0 | Agee Engineering | Auld & White | $350,000 | $320,000 | 6/1/2008 | Work to be done summer 2008. | |
| C-91250 | Baseball & Safety Netting | KT | 3223 | Fletcher, Duncan U. High | Construction | 5% | N/A | Allstate Construction | $180,000 | $170,000 | Construction on Hold pending end of baseball season to start construction. Poles are on site. | ||
| C-91260 | Install Fire Sprinkler system and associated egress improvements | KE | 3033 | Lee, Robert E. High | Design Phase I | 0 | Powell Design Group | TBD | $1,800,000 | $1,200,000 | 9/1/2008 | Design Phase II started. CM selection in progress | |
| C-91270 | Install Fire Sprinkler system and associated egress improvements | KE | 3241 | Forrest, Nathan Bedford High | Design Phase III | 0 | Powell Design Group | TBD | $1,850,000 | $1,200,000 | 9/1/2008 | CM to board June 9, 08. Ph II design completed | |
| C-91290 | Auditorium Seating Replacement and Upgrades | KT | 3237 | Sandalwood High | Construction | 10% | R. Dean Scott Architects, Inc. | Auld & White Construction | $1,575,000 | $999,999 | 12/20/2008 | 7/18/2008 | Construction proceeding |
| C-91300 | Extend Bus Loop Canopy | SR | 3226 | Crystal Springs Elementary | Construction | N/A | Auld and White | $80,000 | $70,000 | 5/15/2008 | Waiting on NTP | ||
| C-91310 | Traffic concerns | AA | 3085 | Lake Lucina Elementary | Design Phase III | Bowen Civil | A&W | $350,000 | $ | 6/30/2008 | Design proceeding | ||
| E-99200 | Server room upgrades for 20 middle schools | SR | DW | DISTRICT WIDE | Construction | 95% | Haddad | Exum | $462,000 | $420,000 | 11/16/2007 | Construction proceeding | |
| E-99300 | Upgrade HVAC at 10 schools | SR | DW | DISTRICT WIDE | Construction | 80% | N/A | AC General | $100,000 | $100,000 | 1/28/2008 | Construction proceeding | |
| E-99300 | Provide infrastructure for FFW Labs at 20 Middle Schools | SR | DW | DISTRICT WIDE | Construction | Searcy | Auld and White | $287,000 | $234,000 | 7/7/2008 | Waiting on NTP | ||
| F-10086 | Design & Install Hurricane Shutters | AA | 3264 | Chets Creek Elementary | Construction | 100 | $82,819 | $ | 4/16/2008 | ||||
| F-10086 | Design and Construction of wind and debris protection for various building envelope openings School No. : 3263, 3264, 3256, 3239, 3258, 3251 | AA | 3239 | Sabal Palm Elementary | Construction | 100 | Baker Klien Engineering | Phoenix Architectural Products | $65,574 | $ | 3/1/2008 | ||
| F-10086 | Design & Install Hurricane Shutters | AA | 3251 | Twin Lakes Academy Elementary | Construction | 100 | Baker Klein Engineering | Kane Manufactoring Corporation | $82,819 | $ | 4/16/2008 | ||
| F-10086 | Design & Install Hurricane Shutters | AA | 3258 | Mandarin Oaks Elementary | Construction | 100 | Baker Klein ngineering | Pheonix Architectural Products | $65,575 | $ | 3/1/2008 | ||
| F-10086 | Design & Install Hurricane Shutters | AA | 3263 | Abess Park Elementary | Construction | 100 | Baker Klein ngineering | Kane Manufacturing Corporation | $82,819 | $ | 4/16/2008 | ||
| F-10086 | Design & Install Hurricane Shutters | AA | 3256 | Landmark Middle | Construction | 50 | Baker Klein Engineering | Kane Manufactoring Corporation | $268,399 | $ | 5/15/2008 | ||
| M-80050 | Install Baseball Field at Highlands Middle School #244. | JP | 3244 | Highlands Middle | Post Occupancy | BHR | TBD | $150,000 | $0 | 2/28/2006 | Project completed | ||
| M-80050 | Tennis Court Complex at Baldwin Middle / High School #38 | JP | 3038 | Baldwin Middle-Senior High | Design Phase I | BHR | TBD | $75,000 | $75,000 | Project completed | |||
| M-80210 | Ktr shall safely and effectively provide termite/ treatment at DCPS facilities district wide per ITB-002-04/CP. | GR | DW | DISTRICT WIDE | Construction | n/a | McCall Service Inc. | $385,000 | $ | The kt was awarded October 03 with the terms of 1 year and 4 renewals at 1 year. | |||
| M-81510 | HVAC -related facility improvements | GR | DW | DISTRICT WIDE | Construction | n/a | Various | $ | $ | The kt was awarded December 06 with the terms of 1 year and 4 renewals at 1year | |||
| M-84670 | Replace Kitchen Floor | SR | 3169 | Hull, Samuel Adams Elementary | Construction | 99% | Auld and White | $31,000 | $31,000 | 2/1/2008 | Project completed | ||
| M-84670 | Repair Fume Hoods in 3 science labs | SR | 3075 | Paxon Advanced | Construction | 100% | MV Cummings | Auld and White | $24,000 | $21,000 | 3/24/2008 | Project completed - waiting on close out docs | |
| M-84670 | Replace Kitchen floor | SR | 3092 | Paxon Middle | Construction | 99% | Auld and White | $41,000 | $41,000 | 2/1/2008 | Project completed | ||
| M-84670 | Replace Kitchen floor | SR | 3236 | Jones, Mamie Agnes Elementary | Construction | 99% | Auld and White | $31,000 | $31,000 | 2/1/2008 | Project completed | ||
| M-84670 | Install continous handrails througout school | SR | 3025 | Kirby-Smith Middle | Construction | 99% | N/A | Auld and White | $25,000 | $23,000 | 2/1/2008 | Project completed | |
| M-84670 | Replace kitchen floor | SR | 3020 | Fishweir Elementary | Construction | 99% | N/A | Auld and White | $39,000 | $39,000 | 2/1/2008 | Project completed | |
| M-84670 | Replace Kitchen floor | SR | 3065 | Atlantic Beach Elementary | Construction | Auld and White | $32,000 | $32,000 | 2/18/2008 | Construction on hold, gas line must be replaced first | |||
| M-84670 | Replace Kitchen Floor | SR | 3064 | Hogan-Spring Glen Elementary | Construction | 99% | Auld and White | $24,000 | $24,000 | 2/1/2008 | Project completed | ||
| M-84670 | Replace Kitchen floor | SR | 3244 | Highlands Middle | Construction | 99% | Auld and White | $42,000 | $42,000 | 2/1/2008 | Project completed | ||
| M-84680 | Plumbing Upgrades Phase III | KT | 3237 | Sandalwood High | Construction | 75% | Bhide & Hall Architects | Auld & White Constructors | $780,000 | $725,000 | 12/14/2007 | 4/18/2008 | Construction proceeding. |
| M-84690 | Replace generator | SR | 3059 | Garden City Elementary | Construction | Haddad | Kim's | $95,000 | $85,000 | 5/7/2008 | Construction started | ||
| M-84690 | Replace Generator | SR | 3069 | Lake Shore Middle | Construction | Haddad | Kim's | $95,000 | $101,000 | 5/17/2008 | Construction started | ||
| M-84690 | Replace Generator | SR | 3014 | Grand Park Career Center | Construction | Haddad | Kim's | $95,000 | $85,000 | 5/10/2008 | Construction started | ||
| M-84710 | Castiron replacement schoolwide | AA | 3075 | Paxon Advanced | Construction | 0 | M.V. Cummings | All State | $1,000,000 | $820,000 | 5/31/2008 | CM selected, contract negotiation started | |
| M-84720 | Replace seating and correct ADA and Code issues | KE | 3241 | Forrest, Nathan Bedford High | Design Phase I | 0 | Powell Design Group | Auld & White | $1,000,000 | $860,000 | 6/6/2008 | Design Phase III started. | |
| M-84730 | Design & Installation of door closers where necessary | AA | 3124 | Evans, Saint Clair Academy | Construction | 90 | Bhide & Hall | Rivers & Rivers | $30,000 | $25,500 | 3/5/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3205 | Pickett Elementary | Construction | N/A | Auld & White | $14,040 | $ | 6/15/2008 | |||
| M-84730 | Design & Installation of door closers where necessary | AA | 3203 | Kings Trail Elementary | Construction | 100 | Bhide & Hall | Rivers & Rivers | $30,000 | $25,500 | 6/15/2008 | ||
| M-84730 | Design & Installation of door closers where necessary | AA | 3091 | Mathis, Sallye B. Elementary | Construction | 90 | Bhide & Hall | Rivers & Rivers | $30,000 | $25,500 | 3/28/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3016 | Ortega Elementary | Construction | 100 | N/A | Auld & White | $18,000 | $ | 6/16/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3020 | Fishweir Elementary | Construction | 50 | N/A | Auld & White | $15,900 | $ | 6/16/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3045 | Dinsmore Elementary | Construction | 50 | N/A | Auld & White | $13,500 | $ | 5/15/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3095 | Pearson, Rutledge H. Elementary | Bidding | N/A | Auld & White | $11,600 | $ | 6/15/2008 | Awaiting GMP | ||
| M-84730 | Design & Install door closers/hardware | AA | 3069 | Lake Shore Middle | Construction | 100 | N/A | Auld & White | $5,320 | $ | 6/15/2008 | Activated CM | |
| M-84730 | Design & Install door closers/hardware | AA | 3149 | Livingston, Smart Pope Elementary | Construction | N/A | Auld & White | $9,000 | $ | 4/8/2008 | |||
| M-84730 | Design & Install door closers/hardware | AA | 3170 | Palm Avenue Exceptional Child Center | Construction | 50 | N/A | Auld & White | $3,400 | $ | 4/8/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3216 | Davis, Jefferson Middle | Construction | N/A | Auld & White | $3,920 | $ | 4/8/2008 | |||
| M-84730 | Design & Install door closers/hardware | AA | 3085 | Lake Lucina Elementary | Construction | 50 | N/A | Auld & White | $16,000 | $ | 4/8/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3241 | Forrest, Nathan Bedford High | Construction | 100 | N/A | Auld & White | $39,400 | $ | 6/15/2008 | ||
| M-84730 | Design & Install door closers/hardware | AA | 3079 | Ramona Blvd. Elementary | Construction | 100 | N/A | Auld & White | $8,500 | $ | 6/15/2008 | ||
| M-84740 | Ft. Caroline Middle School No. 238 | DH | 3238 | Fort Caroline Middle | Design Phase II | 0 | Akel, Logan, Shafer | TBD | $1,010,308 | $ | 5/15/2008 | Design proceeding, Phase III scheduled for April Board | |
| M-84740 | Beauclerc Elementary School No. 230 | DH | 3230 | Beauclerc Elementary | Design Phase III | 0 | Akel, Logan ,Shafer | TBD | $1,093,992 | $ | 5/15/2008 | Design proceeding, Phase III scheduled for April Board | |
| M-84750 | Add electrical outlets all classrooms | SR | 3046 | Arlington Elementary | Construction | 95% | Searcy | Kim's | $40,000 | $25,000 | 3/10/2008 | Project completed - waiting on close outs | |
| M-84750 | Replace main switch gear in main office | SR | 3116 | Tillis, Sadie T. Elementary | Construction | John Searcy & Associates | Kim's Electric | $37,300 | $30,000 | 6/20/2008 | Construction started | ||
| M-84750 | School wide lighting upgrade, non -classroom | SR | 3086 | Parker, Terry High | Construction | 30% | Searcy | Kim's | $115,000 | $90,000 | 3/13/2008 | Construction started | |
| M-84750 | Security lighting for portables | SR | 3237 | Sandalwood High | Construction | 90% | Ohmega | AEC | $46,000 | $36,000 | 3/1/2008 | Construction proceeding | |
| M-84750 | Lighting - Auditorium and Sound Panels | SR | 3153 | Stanton College Preparatory School | Construction | 95% | Searcy | Kim's | $85,000 | $52,000 | 3/13/2008 | Construction proceeding | |
| M-84750 | Lighting Upgrade - Classrooms | SR | 3073 | Love, John Elementary | Construction | 50% | Searcy | Kim's | $73,000 | $57,000 | 5/1/2008 | Construction proceeding | |
| M-84750 | Replace lighting in Building F | SR | 3170 | Palm Avenue Exceptional Child Center | Construction | Ohmega | AEC | $75,000 | $68,500 | 6/9/2008 | Summer Project | ||
| M-84750 | Exterior security lighting | SR | 3090 | Englewood High | Construction | 99% | Ohmega | AEC | $70,500 | $57,000 | 3/1/2008 | Project completed - waiting on close out docs | |
| M-84750 | Replace electrical panels weight rm, wrestling rm, hall T&I bldg and stage | SR | 3241 | Forrest, Nathan Bedford High | Construction | Searcy | Kim's | $278,000 | $261,000 | 6/9/2008 | Summer Project | ||
| M-84750 | Replace main panels in boiler room | SR | 3206 | Brookview Elementary | Construction | Searcy | Kim's | $65,000 | $55,000 | 7/19/2008 | Construction started | ||
| M-84750 | School wide lighting and ceiling tile replacement | SR | 3082 | Love Grove Elementary | Construction | Ohmega | AEC | $335,000 | $292,000 | 6/10/2008 | definite summer project | ||
| M-84750 | Add electrical outlets school wide | SR | 3064 | Hogan-Spring Glen Elementary | Construction | 95% | Searcy | Kim's | $30,400 | $24,000 | 3/13/2008 | Project completed - waiting on closeouts | |
| M-84760 | Building 2, Replace drain lines from classrooms and main drain | AA | 3078 | Biltmore Elementary | Construction | 100 | M.V. Cummings | Auld & White | $85,000 | $31,800 | 4/1/2008 | ||
| M-84760 | Relocate sewer manhole and 100'-8" Sewer Line | AA | 3247 | Finegan, Joseph Elementary | Construction | 100 | M.V. Cummings | Auld & White | $44,000 | $ | 5/1/2008 | ||
| M-84760 | Bldg 4 Replace Sewer to manhole | AA | 3149 | Livingston, Smart Pope Elementary | Construction | 100 | M.V. Cummings | Allstate Construction | $50,000 | $39,900 | 5/1/2008 | ||
| M-84760 | Building 1, replace cast iron drain lines and renovate restrooms | AA | 3068 | Venetia Elementary | Construction | 0 | M.V. Cummings | Allstate Construction | $175,000 | $147,000 | 6/15/2008 | ||
| M-84760 | New water service to band room and gym lobby. Repipe domestic water. | AA | 3063 | Fletcher, Duncan U. Middle | Construction | 50 | M.V. Cummings | Auld & White | $46,000 | $ | 4/1/2008 | ||
| M-84760 | Building 2 Repipe domestic water lines, Building 1 change wall mount toilets to floor mount | AA | 3205 | Pickett Elementary | Bidding | M.V. Cummings | Rivers & Rivers | $200,000 | $167,000 | 6/4/2008 | |||
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3203 | Kings Trail Elementary | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3092 | Paxon Middle | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3162 | Daniels, Roosevelt V. Elementary | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/228 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3265 | First Coast High | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3229 | Jacksonville Heights Elementary | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3260 | Mandarin High | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3006 | Rutherford, Mattie V. Alternative Education Center | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84770 | Replace kitchen hood with new Code compliant hood. | JW | 3158 | Carver, George Washington Elementary | Design Phase III | 0 | Estrella Engineering | TBD | $100,000 | $80,000 | 8/1/2008 | Design Phase II completed. | |
| M-84780 | Repair Spauling Columns, Beams and Walkways | JW | 3086 | Parker, Terry High | Bidding | 0 | Baker-Klein Engineers | Allstate Construction | $250,000 | $ | 6/1/2008 | Awaiting GMP | |
| M-84780 | Repair Spauling Columns, Beams and Walkways | JW | 3096 | Ribault, Jean High | Bidding | 0 | Baker-Klein Engineering | Allstate Construction | $250,000 | $ | 6/1/2008 | Awaiting GMP | |
| M-84780 | Remove Cracked Concrete Ballcourt and Replace | JW | 3256 | Landmark Middle | Construction | 10 | Baker-Klein Engineering | Allstate | $120,000 | $ | 3/29/2008 | Demolition Complete. Desiging Repairs. | |
| M-84790 | Replace Fire Alarm Panel and Devices | SR | 3116 | Tillis, Sadie T. Elementary | Construction | 0 | Haddad Engineering | Allstate | $320,000 | $ | 5/15/2008 | GMP Accepted. Activating Project | |
| M-84790 | Replace Fire Alarm Panel and Devices | JW | 3235 | Fort Caroline Elementary | Construction | 0 | Haddad Engineering | Allstate | $280,000 | $ | 5/1/2008 | GMP Accepted. Activating Project | |
| M-84790 | Replace Fire Alarm Panel and Devices | JW | 3233 | Lone Star Elementary | Construction | 0 | Haddad Engineering | Allstate | $320,000 | $ | 5/15/2008 | 11/14/2008 | GMP Accepted. Activating Project. |
| M-84820 | Replace windows thru out the school | SR | 3220 | King, Martin Luther Jr. Elementary | Construction | 0 | Bhide & Hall | Rivers and Rivers | $477,000 | $454,000 | 6/10/2008 | Construction started | |
| M-84820 | Replace Windows thru out the school | SR | 3077 | Hyde Park Elementary | Construction | 95% | Bhide & Hall | CC Borden | $712,000 | $655,500 | 3/1/2008 | Project completed - need walk through and final | |
| M-84820 | Replace windows thru out the school | SR | 3210 | Oak Hill Elementary | Construction | 5% | Bhide & Hall | Rivers and Rivers | $573,000 | $443,800 | 6/10/2008 | Construction started | |
| M-84820 | Replace windows thru out the school | SR | 3063 | Fletcher, Duncan U. Middle | Construction | 10% | Bhide & Hall | CC Borden | $288,000 | $264,000 | 4/30/2008 | Construction started | |
| M-84820 | Replace all windows thru out the school | SR | 3216 | Davis, Jefferson Middle | Post Occupancy | 100% | Design Works | Auld & White | $820,000 | $750,000 | 8/1/2007 | Post occupancy and warranty phase | |
| M-84820 | Replace windows bldg's 3, 4 and 5 | SR | 3153 | Stanton College Preparatory School | Design Phase III | Pond | $421,400 | $370,000 | Design proceeding | ||||
| M-84820 | Replace windows all buildings | SR | 3207 | Stuart, J.E.B. Middle | Design Phase III | Pond, Junck and Walker | $526,000 | $480,000 | Design proceeding | ||||
| M-84820 | Replace all Windows thru out the school | SR | 3097 | Cedar Hills Elementary | Construction | 5% | Bhide & Hall | Allstate | $698,000 | $624,000 | 5/20/2008 | Construction started | |
| M-84820 | Replace windows at bldg's 1, 3, 4 and 5 | SR | 3066 | duPont, Alfred I. Middle | Design Phase III | Pond | $208,000 | $180,000 | Design proceeding | ||||
| M-84840 | Install new CCTV head end, cabling and conduit | SR | 3048 | Jefferson, Thomas | Construction | 99% | Haddad Engineering | EXUM | $95,000 | $88,415 | Project completed, waiting on close out docs. | ||
| M-84850 | Improve drainage at resource center building | SR | 3096 | Ribault, Jean High | Design Phase I | Bowen | $50,000 | $ | Design Phase started | ||||
| M-84850 | Site Drainage | SR | 3258 | Mandarin Oaks Elementary | Construction | 100% | Bowen | Auld-White | $60,000 | $ | Project completed - waiting on close outs. | ||
| M-84870 | Replace water valves | SR | 3253 | Twin Lakes Academy Middle | Construction | N/A | Auld and White | $5,832 | $5,832 | 6/2/2008 | Construction started | ||
| M-84870 | Sink upgrade | SR | 3066 | duPont, Alfred I. Middle | Construction | N/A | Auld and White | $7,363 | $7,363 | Waiting on NTP | |||
| M-84870 | Field House bathroom upgrade | SR | 3224 | Wolfson, Samuel W. High | Construction | N/A | Auld and White | $47,352 | $47,352 | 6/2/2008 | Construction started | ||
| M-84870 | Replace sewer line | SR | 3206 | Brookview Elementary | Construction | N/A | Auld and White | $13,714 | $13,714 | 6/2/2008 | Construction started | ||
| M-84880 | Replace fire alarm | SR | 3143 | West Jacksonville Elementary | Construction | 99% | SEARCY | EXUM | $150,000 | $178,614 | 8/6/2007 | Project completed, waiting on close out docs. | |
| M-84880 | Replace fire alarm | SR | 3066 | duPont, Alfred I. Middle | Bidding | OHMEGA | Auld and White | $400,340 | $349,340 | Waiting for NTP | |||
| M-84880 | Replace fire alarm | SR | 3203 | Kings Trail Elementary | Construction | 95% | OHMEGA | GAYCO | $250,000 | $207,000 | Project completed, waiting on close out docs. | ||
| M-84880 | Replace fire alarm system | SR | 3038 | Baldwin Middle-Senior High | Construction | 95% | SEARCY | EXUM | $355,604 | $291,000 | 8/6/2007 | Construction proceeding | |
| M-84880 | Replace fire alarm | SR | 3158 | Carver, George Washington Elementary | Construction | 99% | SEARCY | EXUM | $250,000 | $208,205 | 8/6/2007 | Project completed, waiting on close out docs. | |
| M-84890 | Palm Ave Exceptional No. 170 | DH | 3170 | Palm Avenue Exceptional Child Center | Construction | 15 | Akel, Logan, Shafer | BBG | $53,625 | $ | 11/1/2007 | Construction proceeding, Part of a 6 school package | |
| M-84890 | Urban Resource Center No 275 | DH | 3275 | Urban Resource Center | Bidding | 95 | Akel, Logan, Shafer | BBG | $146,770 | $ | 11/1/2007 | Construction proceeding, Part of a 6 school package | |
| M-84890 | Alden Road Exceptional No. 252 | DH | 3252 | Alden Road Exceptional Child Center | Construction | 40 | Akel,Logan,Shafer | BBG | $333,058 | $ | 11/1/2007 | Construction proceeding | |
| M-84890 | Lone Star Elementary No. 233 | DH | 3233 | Lone Star Elementary | Construction | 95 | Akel Logan Shafer | BBG | $87,796 | $ | 11/1/2007 | Construction proceeding, Part of a 6 school package | |
| M-84890 | Atlantic Beach Elementary No. 65 | DH | 3065 | Atlantic Beach Elementary | Construction | 15 | Akel ,Logan, Shafer | BBG | $131,817 | $ | 11/1/2007 | Construction started, Part of a 6 school package | |
| M-84890 | Mayport Elementary School No. 227 | DH | 3227 | Mayport Elementary | Construction | 80 | Akel, Logan, Shafer | BBG | $33,727 | $ | 11/1/2007 | Construction proceeding, Part of a 6 school package | |
| M-84890 | John E. Ford Elementary No. 154 | DH | 3154 | Ford, John E. Elementary | Construction | 30 | Akel, Logan, Shafer PA | Advanced Roofing | $986,514 | $785,000 | 9/1/2007 | Construction started | |
| M-84920 | Replace non-compliant doors and add doors for secondary egress | KE | 3227 | Mayport Elementary | Construction | 0 | Akel Logan Shaffer | CC Borden | $87,150 | $65,000 | 4/28/2008 | 2/26/2008 | Construction started (material on order) - Start after spring break |
| M-84920 | Replace non-compliant main entrance doors | KE | 3162 | Daniels, Roosevelt V. Elementary | Construction | 0 | Akel Logan Shaffer | CC Borden | $65,500 | $50,000 | 4/24/2008 | 2/26/2008 | Construction started (material on order) |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3224 | Wolfson, Samuel W. High | Construction | Bhide & Hall | Auld & White | $21,200 | $ | 6/6/2008 | |||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3153 | Stanton College Preparatory School | Construction | 0 | Bhide & Hall | Auld & White | $29,400 | $ | 4/8/2008 | ||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3244 | Highlands Middle | Design Phase II | 0 | Bhide & Hall | Auld & White | $20,000 | $17,000 | 6/12/2008 | Design proceeding | |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3170 | Palm Avenue Exceptional Child Center | Construction | 0 | Bhide & Hall | Auld & White | $21,720 | $ | 4/8/2008 | ||
| M-84920 | Replace non-compliant doors and add doors for secondary egress | KE | 3242 | Sheffield, Louis Elementary | Construction | 10 | Akel Logan Shaffer | CC Borden | $151,680 | $128,000 | 3/28/2008 | 2/26/2008 | Construction proceeding |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3267 | LaVilla School of the Arts | Construction | Bhide & Hall | Auld & White | $6,240 | $ | 4/18/2008 | |||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3208 | Parkwood Heights Elementary | Construction | 0 | Bhide & Hall | Allstate | $100,500 | $ | 5/13/2008 | ||
| M-84920 | Design & Install door closers/hardware | AA | 3213 | Arlington Middle | Construction | N/A | Auld & White | $21,000 | $ | 4/8/2008 | |||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3059 | Garden City Elementary | Design Phase III | 0 | Bhide & Hall | Allstate Construction | $45,000 | $ | 5/12/2008 | Design proceeding | |
| M-84920 | Design & Install door closers/hardware | AA | 3236 | Jones, Mamie Agnes Elementary | Construction | N/A | Auld & White | $20,740 | $ | 4/8/2008 | |||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3091 | Mathis, Sallye B. Elementary | Design Phase III | 0 | Bhide & Hall | TBD | $12,750 | $21,250 | 4/5/2008 | Design proceeding | |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3083 | San Jose Elementary | Design Phase III | 0 | Bhide & Hall | TBD | $95,000 | $ | 5/12/2008 | Design proceeding | |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3084 | Bayview Elementary | Design Phase III | 0 | Bhide & Hall | Allstate | $42,500 | $ | 5/13/2008 | Design proceeding | |
| M-84920 | Replace non-compliant classroom doors in bldg 3 | KE | 3078 | Biltmore Elementary | Construction | 0 | Akel Logan Shaffer | CC Borden | $105,620 | $97,000 | 4/24/2008 | 3/3/2008 | Construction in late April |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3096 | Ribault, Jean High | Design Phase II | 0 | Bhide & Hall | TBD | $25,000 | $ | 4/12/2008 | Design proceeding | |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3077 | Hyde Park Elementary | Design Phase III | 0 | Bhide & Hall | TBD | $15,000 | $ | 6/12/2008 | Design proceeding | |
| M-84920 | Design & Install Doors and Door Hardware | AA | 3015 | Brentwood Elementary | Construction | 100 | Bhide & Hall | Rivers & Rivers | $31,300 | $ | 4/1/2007 | ||
| M-84920 | Replace non-compliant classroom doors | KE | 3166 | Woodson, Carter G. Elementary | Construction | 0 | Akel Logan Shaffer | CC Borden | $134,000 | $100,000 | 5/20/2008 | 7/31/2008 | Construction on Hold - summer 08 project |
| M-84920 | Install Door Closers & Door Magnets | AA | 3001 | Central Administration Building | Construction | N/A | Auld & White | $21,400 | $ | 6/15/2008 | |||
| M-84920 | Design & Install door closers/hardware | AA | 3254 | Mayport Middle | Construction | N/A | Auld & White | $23,090 | $ | 6/15/2008 | |||
| M-84920 | Design & Install door closers/hardware | AA | 3098 | Timucuan Elementary | Construction | N/A | Auld & White | $15,800 | $ | 4/8/2008 | |||
| M-84920 | Various Hardware and Door Access Replacement | AA | 3228 | Merrill Road Elementary | Construction | N/A | Auld & White | $90,000 | $ | 6/20/2008 | |||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3073 | Love, John Elementary | Construction | 0 | Bhide & Hall | Allstate | $95,000 | $85,000 | 5/13/2008 | ||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3066 | duPont, Alfred I. Middle | Design Phase III | Bhide & Hall | TBD | $50,000 | $ | 5/12/2008 | Design proceeding | ||
| M-84920 | Design & Install Doors and Door Hardware | AA | 3086 | Parker, Terry High | Bidding | 0 | Bhide & Hall | Allstate | $103,200 | $ | 5/13/2008 | ||
| M-84930 | Compliant door landings at various schools (# 10, 30, 32, 38, 153, 136, 216, 94) | KE | DW | DISTRICT WIDE | Construction | 20 | Bhide & Hall | Rivers | $200,000 | $150,000 | 12/15/2007 | 3/15/2008 | # 38 complete. # 94 90% complete. Others start spring break |
| M-84940 | Provide / improve egress from CRs, relocate greenhouse | KE | 3225 | Seabreeze Elementary | Construction | 85 | Junck & Walker | River & Rivers | $307,000 | $260,000 | 12/15/2007 | 4/1/2008 | Construction proceeding -demo in progress over spring break. |
| M-84940 | Provide / improve egress from locker room | KE | 3165 | Raines, William High | Construction | 80 | Junck & Walker | River & Rivers | $45,000 | $130,000 | 11/1/2007 | 1/20/2008 | Egress doors for locker rooms - Construction in progress |
| M-84940 | Provide / improve egress from locker room & CRs | KE | 3165 | Raines, William High | Construction | 98 | Junck & Walker | River & Rivers | $75,000 | $600,000 | 5/25/2007 | Egress doors pending AE / Code inspections | |
| M-84940 | Provide / improve egress from CR 115, seal holes in corridors | KE | 3246 | Neptune Beach Elementary | Construction | 90 | Junck & Walker | River & Rivers | $100,000 | $80,000 | 5/29/2007 | Substantially complete, punchlist started | |
| M-84960 | AA | 3209 | Holiday Hill Elementary | Construction | 75 | Bhide & Hall | C.C. Borden | $55,480 | $49,000 | 12/17/2007 | |||
| M-84960 | AA | 3149 | Livingston, Smart Pope Elementary | Construction | 75 | Bhide & Hall | C.C. Borden | $47,384 | $41,400 | 12/17/2007 | |||
| M-84960 | AA | 3213 | Arlington Middle | Construction | 75 | Bhide Hall | C.C. Borden | $47,160 | $17,200 | 12/17/2007 | |||
| M-84960 | Egress improvements, window replacement, CR improvements | KE | 3164 | Mt. Herman Exceptional Child Center | Construction | 57 | Design Works | Auld & White | $1,825,000 | $1,360,000 | 12/17/2007 | Construction proceeding - CR 12, 15,16 complete. CR 1,3,5 in progress | |
| M-84960 | Canopy, bus loop & parent loop | KE | 3252 | Alden Road Exceptional Child Center | Construction | 30 | Dsign Works | Rivers | $650,000 | $590,000 | 8/1/2007 | 2/15/2007 | Construction proceeding -bus lane complete. Canopy planned for summer 08 |
| M-84960 | AA | 3252 | Alden Road Exceptional Child Center | Construction | 50 | Bhide & Hall | C.C. Borden | $2,950 | $11,700 | 12/17/2007 | |||
| M-84960 | AA | 3066 | duPont, Alfred I. Middle | Construction | 75 | Bhide & Hall | C.C. Borden | $45,720 | $41,600 | 12/17/2007 | |||
| M-84960 | AA | 3265 | First Coast High | Construction | 75 | Bhide & Hall | C.C. Borden | $27,640 | $22,400 | 12/17/2007 | |||
| M-84960 | AA | 3092 | Paxon Middle | Construction | 75 | Bhide & Hall | C.C. Borden | $63,780 | $56,400 | 12/17/2007 | |||
| M-84960 | AA | 3086 | Parker, Terry High | Construction | 75 | Bhide & Hall | C.C. Borden | $47,160 | $22,200 | 12/17/2007 | |||
| M-84970 | Cable Tray Repair/Replacement | SR | 3096 | Ribault, Jean High | Construction | EXUM | $40,200 | $25,000 | 6/10/2008 | Construction started | |||
| M-84970 | Replace generator | SR | 3165 | Raines, William High | Bidding | N/A | Auld and White | $53,226 | $53,226 | Waiting on NTP | |||
| M-84970 | Replace 2000a switchgear | SR | 3148 | Brown, Richard L. Elementary | Bidding | N/A | Auld and White | $34,923 | $34,923 | Waiting on NTP | |||
| M-84980 | Plumbing Upgrades Phase III & Chiller cool-down loop | KT | 3238 | Fort Caroline Middle | Construction | 85% | Bhide & Hall Architects | Auld & White Constructors | $825,000 | $744,450 | 6/11/2007 | 2/8/2008 | Construction proceeding. |
| M-85030 | Provide accessible ramps to gym | KE | 3063 | Fletcher, Duncan U. Middle | Bidding | 0 | Baker Klein | TBD | $25,000 | $20,000 | 4/25/2008 | CM selection in progress | |
| M-85030 | Provide accessible restrooms in Bldg 5. Provide accessible route from portables. | KE | 3069 | Lake Shore Middle | Bidding | 0 | Powell Design Group | Auld & White | $111,300 | $90,000 | 3/20/2008 | GMP received. Activation in progress | |
| M-85030 | Provide auto door openers and accesible doors in various rooms | KE | 3280 | Peterson, Frank H. Academies of Technology | Construction | 85 | Bhide & Hall | Rivers & Rivers | $120,000 | $95,000 | 12/15/2007 | Construction proceeding | |
| M-85030 | Provide accessible route in admin area for staff & visitors. | KE | 3206 | Brookview Elementary | Pre-Planning | 0 | DesignWorks/ Powell Design Group | Auld & White | $149,100 | $121,100 | 6/1/2008 | GMP received. | |
| M-85250 | Remodel band and sciece labs. | KT | 3145 | Darnell-Cookman Middle | Post Occupancy | 100% | Bhide and Hall | Auld and White | $312,500 | $240,000 | 6/4/2007 | 8/10/2007 | Post occupancy and warranty phase |
| M-85290 | Replacement of 12 roof top units and minor plumbing upgrades. | KT | 3063 | Fletcher, Duncan U. Middle | Pre-Planning | 0% | M.V. Cummings | Weather Engineering | $327,000 | $240,000 | 2/18/2007 | A/E selected, contract negotiation started | |
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3099 | Highlands Elementary | Bidding | 0 | MV Cummings | Allstate Construction | $41,950 | $35,875 | Need Additional Funding | ||
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3020 | Fishweir Elementary | Post Occupancy | 0 | MV Cummings | Allstate Construction | $41,950 | $35,875 | 3/31/2008 | Completed Spring Break | |
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3059 | Garden City Elementary | Bidding | 0 | MV Cummings | Allstate Construction | $41,950 | $35,875 | Need Additional Funding | ||
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3223 | Fletcher, Duncan U. High | Bidding | 0 | MV Cummings | Allstate Construction | $10,000 | $8,000 | Need Additional Funding | ||
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3221 | Normandy Village Elementary | Bidding | 0 | MV Cummings | Allstate Construction | $30,000 | $27,000 | 6/30/2008 | Awaiting GMP | |
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3224 | Wolfson, Samuel W. High | Bidding | 0 | MV Cummings | Allstate Construction | $4,000 | $3,000 | Need Additional Funding | ||
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3078 | Biltmore Elementary | Bidding | 0 | MV Cummings | Allstate | $48,000 | $40,000 | 6/30/2008 | Awaiting GMP | |
| M-85300 | Replace Kitchen Hood with New Code Compliant Hood | JW | 3169 | Hull, Samuel Adams Elementary | Bidding | ) | MV Cummings | Allstate Construction | $41,950 | $35,875 | Need Additional Funding | ||
| M-85310 | Replace HVAC equipment, piping, insulation and controls | JW | 3285 | Randolph, A. Philip Academies of Technology | Construction | 35 | Paryani Engineers | AC General | $3,000,000 | $2,645,000 | 6/1/2007 | Several areas completed. Bulk of remaining to be completed summer 2008. | |
| M-85320 | Replace HVAC equipment, piping, insulation, controls, electrical service, etc., at various schools (3002, 3014, 3035, 3048, 3092, 3146, 3169, 3230, 3239, 3247, 3249, 3250, 3258) | SC | DW | DISTRICT WIDE | Post Occupancy | 100 | Eng Engineering | Johnson Controls | $1,803,000 | $1,583,000 | 5/1/2007 | Punchlist progressing | |
| M-85350 | Renovation of stadium Facilities | KT | 3035 | Jackson, Andrew High | Construction | 5% | Pond Junck and Walker | Ajax | $1,305,300 | $1,214,250 | 2/6/2008 | 7/31/2008 | Construction proceeding |
| M-85360 | Updating card readers, door contacts, access panels and power supplies at School # 149 | SR | 3149 | Livingston, Smart Pope Elementary | Bidding | 0 | Haddad Engineering | $124,832 | $115,832 | On hold for additional funding | |||
| M-85370 | New Parking Lot & Drainage | KT | DW | DISTRICT WIDE | Construction | 50% | Bowen Civil Engineering | Allstate Construction | $350,000 | $323,000 | 9/17/2007 | 1/9/2008 | Substantially complete, punchlist in process |
| M-85380 | Design and Installation of new Grease Traps | AA | 3046 | Arlington Elementary | Construction | 100 | M.V. Cummings | Rivers & Rivers | $38,569 | $ | 1/31/2008 | ||
| M-85380 | AA | 3094 | Windy Hill Elementary | Bidding | M.V. Cummings | TBD | $40,220 | $36,150 | 8/1/2008 | Current GMP far exceeds budget, awaiting additional pricing | |||
| M-85380 | AA | 3241 | Forrest, Nathan Bedford High | Construction | M.V. Cummings | Auld & White | $36,368 | $ | 6/30/2008 | ||||
| M-85380 | Design & Install Grease Traps | AA | 3208 | Parkwood Heights Elementary | Construction | 100 | M.V. Cummings | Auld & White | $49,526 | $41,450 | |||
| M-85380 | Design & Install Grease Interceptors | AA | 3214 | Hyde Grove Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/1/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | ||
| M-85380 | AA | 3215 | Justina Road Elementary | Construction | M.V. Cummings | Auld & White | $41,540 | $36,150 | 6/1/2008 | ||||
| M-85380 | Design & Install Grease Interceptors | AA | 3077 | Hyde Park Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | ||
| M-85380 | AA | 3014 | Grand Park Career Center | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | AA | 3225 | Seabreeze Elementary | Construction | 100 | M.V. Cummings | Auld & White | $45,338 | $36,150 | 4/1/2008 | |||
| M-85380 | Design & Install Grease Traps | AA | 3206 | Brookview Elementary | Bidding | M.V. Cummings | TBD | $40,770 | $36,150 | 8/1/2008 | CM selection in progress | ||
| M-85380 | AA | 3064 | Hogan-Spring Glen Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | Design & Install of Grease Traps | AA | 3170 | Palm Avenue Exceptional Child Center | Construction | 100 | M.V. Cummings | Rivers & Rivers | $37,226 | $36,150 | 6/30/2008 | ||
| M-85380 | AA | 3019 | Upson, Ruth N. Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | AA | 3238 | Fort Caroline Middle | Construction | M.V. Cummings | TBD | $59,620 | $33,750 | 8/1/2008 | Pre-Construction | |||
| M-85380 | AA | 3018 | Central Riverside Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | Design & Install Grease Interceptors | AA | 3233 | Lone Star Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/1/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | ||
| M-85380 | AA | 3012 | West Riverside Elementary | Design Phase I | M.V. Cummings | TBD | $ | $ | 6/17/2009 | Design Phase started $4200 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | AA | 3224 | Wolfson, Samuel W. High | Construction | M.V. Cummings | Auld & White | $41,870 | $36,150 | 8/1/2008 | ||||
| M-85380 | AA | 3207 | Stuart, J.E.B. Middle | Bidding | M.V. Cummings | TBD | $ | $ | 6/1/2009 | Design Phase started $6667 activated for design Construction Phase Unfunded, Awaiting Programming | |||
| M-85380 | AA | 3071 | Hendricks Avenue Elementary | Construction | 100 | M.V. Cummings | Auld & White | $51,520 | $ | 6/30/2008 | |||
| M-85380 | Design & Install of Grease Traps | AA | 3153 | Stanton College Preparatory School | Construction | ||||||||